Preparation for commissioning
The customer must make the following arrangements before the
machine is commissioned by the TRUMPF service engineer:
■
Transport the machine to the installation site (see Chapter 6,
Transport).
■
Position the machine and drill holes for the anchor bolt (see
Chapter 7, Installation).
■
Position the adjustable legs provided for the purpose
beneath the machine (see Chapter 8, Set-up).
■
Assemble the support brackets provided (see Chapter 9,
Support bracket).
■
Connect the foot switch and network cable (see Chapter 10,
Foot switch and network cable).
■
Have the machine connected to the power supply by an
electrician (see Chapter 11, Electrical connection).
The work steps for this are described in the following Chapters.
B1161en
Preparation for commissioning - Version 1