Triple Solar assembly instruction PVT heat pump panels March 2020

Attention:

Always place the expansion vessel in the source circuit on the suction side of the pump, and as 

close to the pump as possible.

Attention:

It is not recommended to use automatic air vents in the source circuit, as these become 

unreliable in the long run when the condensate freezes and may leak. However, there is an 

automatic air vent in the expansion vessel connection group. Here there is less variation in 

temperature

Filling medium

The source liquid must have a freezing point of -20 °C. A safety margin has been taken into 

account. The maximum operating temperatures of the Triple Solar system are -12 °C and +30 °C

The heat pump switches off automatically outside this temperature range. 

Triple Solar supplies a water antifreeze mixture consisting of 35% ethylene glycol (TYFOCOR from 

Tyfo). 

Triple Solar supplies a water-antifreeze mixture consisting of 40% propylene glycol when 

connected to a cooling module. (regarding KIWA requirements)

Mono-propylene or bio-glycol is also possible, but these types of glycol work less well at lower 

temperatures due to a higher viscosity. 

Observe the supplier's instructions regarding concentration ratio, toxicity and safety.

Check the mixing ratio of the glycol with a refractor device. Make sure the refractor device is 

suitable for ethylene or propylene glycol.

Attention:

In case of doubt about the mixing ratio of the glycol, check with a refractor device. Make sure that 

the refractor device is suitable for ethylene or propylene glycol. 

Installing the expansion vessel

Mounting the expansion vessel:

In the suction side of the system. This is in the warm side of the well! (see diagram in figure 8.4-

a). (This is different from continuous heating installations where the expansion vessel is also 

placed in the suction side, but in the cold side).

As close as possible to the pump 

Note that the type of expansion vessel is suitable for ethylene glycol. Often referred to with the 

addition "solar".

For installations with a heat pump of 12kW or more, it is advisable to have the size of the expansion 

vessel determined in consultation with the supplier. In addition to the capacity of the heat pump, 

location, water content and temperature also play a role.

Connecting thermostatic mixing valve

The thermostatic mixing valve must be set to 25 °C or setting 4 on the Esbe mixing valve (this 

applies to NIBE heat pumps).

Содержание M2 300 165 landscape

Страница 1: ...manual heat pump panels triple solar heating without gas...

Страница 2: ...gning panels and installing roof brackets 8 6 Preparation for a flat roof 12 7 Installation of the panels 13 Placing the TS clamping profile 13 Mounting of the panels 14 Mounting the TS clamping profi...

Страница 3: ...surface during installation Stop the installation in case of strong gusts of wind Provide lightning protection during assembly in accordance with building regulations Legal requirements standards and...

Страница 4: ...ion PVT heat pump panels March 2020 2 Technical information Measures Model M2 360 200 landscape Model M2 300 165 landscape Figure 2 1 a heat pump panel type M2 360 200 landscape Figure 2 1 b heat pump...

Страница 5: ...8 1 65 materials PV panel Glass Heat exchanger tubes Copper Heat exchanger fins Aluminium Finishing Kataforese 3 Placement of the panel field Inclination angle on flat roof Mount heat pump panels at a...

Страница 6: ...ption Specification Image 322101 324201 Mounting rail 2120 mm 4200 mm 330101 Mounting rail connector Aluminium with M8 flange nuts 310300 TS clamping profile slide connector Assembly of plastic and st...

Страница 7: ...dditional components required for flat roof installation Art nr Description Specification Aantal Image 300510 Flat roof frames first panel south per row Sunbeam Universal 1x per panel Zie figure 4 3 a...

Страница 8: ...d fill connection set 1 inside DN25 500100 Expansion vessel 18 L 500150 Expansion vessel connection group Including automatic air vent pressure gauge and pressure relief valve 3 bar 800010 TS crane gr...

Страница 9: ...ting the installation Four roof brackets are required per panel 2 Screws are included per roof bracket 7 0x50 stainless steel Attention The dimensions in figure 5 1 a are critical If they are not resp...

Страница 10: ...p panels March 2020 Figure 5 1 b Pitched roof alignment diagram dimensions in mm The lengths can differ per type of panel Attach the roof brackets if necessary with extra underlayment wood to get the...

Страница 11: ...ghten the mounting rail by tightening the flange nut of the cross connector to 26Nm drive SW13 See also figure 5 1 d as an example If more than one rail is to be connected insert the mounting rail con...

Страница 12: ...wind convection runs underneath them This has an effect on the heat exchange capacity of the heat pump panels The minimum distance between the roof and the underside of the heat pump panels is 90mm T...

Страница 13: ...plan of the Sunbeam Calculator for the ballast distribution 1 After assembling the Sunbeam mounting system the Triple Solar mounting rails 324200 must be fixed to the Sunbeam triangles by means of cr...

Страница 14: ...d at the back side of the heat pump panels This TS clamping profile is required due to wind and tensile loads at the centre of the heat pump panel The aluminium frame that surrounds PV panels and prov...

Страница 15: ...to a hole in the end profile on each side of the heat pump panel to prevent it from slipping See figure 7 2 a Figure 7 2 a panel with M8 bolt to prevent slipping 2 Lay down the outer heat pump panel a...

Страница 16: ...igure 7 2 c connecting hoses mounted on one side 6 Place the next panel on the rails and secure with the M8 bolts against slipping Carefully push the entire panel sideways in one controlled movement t...

Страница 17: ...d middle clamp Mounting the TS clamping profile Now that the whole row of panels is in place and it has been checked that the alignment of the panels is correct it is time to connect TS clamping profi...

Страница 18: ...with a D Connecting the PV panels electrically The instruction for the electrical connection of the heat pump panels is identical to regular PV panels The electrical connection may only be carried ou...

Страница 19: ...view for connecting optimizers It is important to avoid large induction loops in order to ground the PV cables correctly The correct way is to lay the electrical cables next to each other as much as...

Страница 20: ...ource fluid Make sure that the flow in the source circuit is limited as little as possible e g by using knees and or pipes with an inner diameter that is too small Do not install any piping under the...

Страница 21: ...n connection Attention Preferably connect the panel according to the Tichelman principle connect the cold pipe at the bottom of the panels the hot return pipe at the top Fittings Preferably use squeez...

Страница 22: ...hose package 1 6x connection plug outside 2 3x valve inside outside 3 2x ribbed hose inside outside 900 1300mm 4 2x adapter x1 inside outside 5 4x T adapter 1 x x1 inside 6 2x ribbed hose 1 inside out...

Страница 23: ...the panel field 6 kW to 8kW 26 mm 8 kW to 15kW 32 mm 15kW to 28kW 41 mm 28kW to 50kW 51 mm Hydraulic plan Fit a 3 bar pressure relief valve or use the supplied expansion vessel connection group 3 bar...

Страница 24: ...er temperatures due to a higher viscosity Observe the supplier s instructions regarding concentration ratio toxicity and safety Check the mixing ratio of the glycol with a refractor device Make sure t...

Страница 25: ...with the following insulation properties Vapour tight 19mm thick Minimum thermal conductivity 0 033 W mK For fixing the piping to the wall the following support is recommended to prevent cold bridges...

Страница 26: ...101 mounting rail cover aluminium black anodising 2x 336101 Self drilling screw with EPDM ring 4 8x25mm stainless steel SW8 4x Instructions see corresponding images below 1 Slightly bend the mounting...

Страница 27: ...remaining drinking water will affect the glycol ratio in the system The warranty provided by Triple Solar and Nibe expires with immediate effect Always first pressurize the installation with air to d...

Страница 28: ...long and removed from the pipe system All loops are flushed sequentially After flushing the field is filled Careful venting System pressure at heat pump 2 4 bar System pressure on the roof Pressure on...

Страница 29: ...conditions see www triplesolar eu Points of attention here Warranty conditions products Triple Solar gives a product warranty on the heat pump panels for a period of 10 years PV panels heat pumps and...

Отзывы: