background image

AM-4 Interface Module Kit

5

0 TO 10 VDC EXTERNAL CAPACITY WITH
PARAMETER

In this application the external boiler controller will
control the modulation of the multiple Prestige
Boilers based on the system load requirements.  

The external controller will provide a 0 to 10 vdc
analog input to the Prestige AM4 interface module
based on the time to meet the system load require-
ments.  The initial analog input of 1.8 vdc or less will
indicate the minimum load.  An analog input of 10
vdc will indicate the maximum load requirements.
The actual function of the external controller will
vary from manufacturer to manufacturer.

To configure the MCBA control to react based on
the output signal of an external boiler controller
Parameter 34 must be revised accordingly.

Parameter Adjustment

The adjustment of Parameter 34 in the CODE mode
is done by following the steps given in Program
Access Section on page 3 until the display shows

P_34

.  Use the + or - to adjust to the revised set-

ting listed below and press STORE to save the set-
ting.

Test / Verify Boiler and Control Operation

1.  Refer to and follow the instructions given in the

Prestige Installation manual to test operation of
the boiler and the MCBA control.  To initiate
any calls for heat during the test you will have
to operate the external boiler controller.

2.  Verify the boiler modulates correctly by adjust-

ing the external boiler controller.

3.  The boiler MCBA control response to the exter-

nal 0 - 10 vdc analog signal should be:

-

Boiler ON for a signal voltage above 0.5
vdc

-

Boiler at low input fire rate for a signal volt-
age between 0.5 vdc and 1.8 vdc.

-

Boiler at high input fire rate for a signal
voltage of 10 vdc.

-

Boiler will modulate the input fire rate
between high and low inputs for a signal
voltage between 1.8 vdc and 10 vdc.

This test and verification procedure only

applies to an external boiler controller that

reacts to the system load requirements.  For

information on testing and verifying the

operation of a boiler control that reacts to the

temperature conditions of the system, con-

tact Triangle Tube Engineering Department.

NOTICE

Parameter

Factory Setting

Revised Setting

P_34

00

04

Содержание PSRKIT23

Страница 1: ...uipment but not related to personal injury hazards NOTICE WARNING Failure to follow instructions below can result in severe personal injury or damage if ignored Instructions are for a qualified installer service technician Read all instructions before proceeding Follow instructions in the proper order For your safety turn off electrical power supply at service panel and allow unit to cool before p...

Страница 2: ...wires through the wire ways of the Prestige boiler and along the Prestige factory wiring Strip the wire ends and connect to the AM 4 terminals X2 1 and X2 2 for the 0 10 vdc analog signal and X1 1 and X1 2 for the alarm as shown in Figure 1 Use the cable clamps pro vided in the AM 4 kit to secure the incoming wires to the module Ensure the polarity of the wire connections from the Boiler Controlle...

Страница 3: ...ule operational parameter settings reference the Prestige Control Supplement Program Access To enter the parameter listing of the MCBA control the installer must enter the activation code as fol lows 1 Press and hold the MODE button 2 Continue holding the MODE and press STEP button until STBY appears and hold both STEP and MODE buttons for 2 to 3 seconds The display should read CODE 3 Release the ...

Страница 4: ...hange the value of the display Press the STORE button once to save the change If a parameter setting is changed from the factory default and the STORE button is not pressed to save the setting the MCBA mod ule will automatically store the setting after 15 minutes Ensure all parameters settings are either factory default or revised based on the application Review all parameters set tings on page 10...

Страница 5: ...ing listed below and press STORE to save the set ting Test Verify Boiler and Control Operation 1 Refer to and follow the instructions given in the Prestige Installation manual to test operation of the boiler and the MCBA control To initiate any calls for heat during the test you will have to operate the external boiler controller 2 Verify the boiler modulates correctly by adjust ing the external b...

Страница 6: ... to use the wire tool to remove the jumper from the terminal block 2 Restore power to the boiler initiate a demand and allow the boiler to proceed through its start up sequence 3 The Prestige MCBA control module should enter a hard lockout causing the alarm contacts on the AM 4 to close The remote alarm should then be activated 4 Disconnect the power supplied to the boiler and replace the jumper a...