Forms
Checklist for Completed Installation
Proper clearances for service access have been
maintained around equipment.
Equipment is level and mounting fasteners are tight.
Piping completed to refrigeration equipment.
All field installed piping leak tested.
Refrigerant charge added.
Incoming line voltage matches equipment nominal
nameplated rating ± tolerances.
Main power wiring connections to the equipment,
including earth ground, have been properly installed.
Customer supplied main power circuit breaker (HACR
type) or fuses have proper ratings for equipment
installed.
Control wiring connections completed to remote
condensing unit.
All wiring connections are tight.
Foreign materials have been removed from inside and
around all equipment installed (shipping materials,
construction materials, tools, etc.).
Compressor and fan rotate freely without unusual
noise.
Inspect all piping connections for leaks during initial
operation.