T_C-IOM-2A
32
Final System Setup
After completing all of the pre-start and
start-up procedures outlined in the previ-
ous sections (i.e., operating the unit in
each of its Modes through all available
stages of cooling & heating), perform
these final checks before leaving the unit:
[ ] Program the Night Setback (NSB)
panel (if applicable) for proper unoc-
cupied operation. Refer to the pro-
gramming instructions for the specific
panel.
[ ] Verify that the Remote panel “Sys-
tem” selection switch, “Fan” selection
switch, and “Zone Temperature” set-
tings for automatic operation are cor-
rect.
[ ] Inspect the unit for misplaced tools,
hardware, and debris.
[ ] Verify that all exterior panels including
the control panel doors and condenser
grilles are secured in place.
[ ] Close the main disconnect switch or cir-
cuit protector switch that provides the
supply power to the unit’s terminal
block or the unit mounted disconnect
switch.
Final System Set Up
Содержание Precedent TSC060
Страница 25: ...25 T_C IOM 2A Installation Figure 6 Typical Field Wiring Diagrams for Optional Controls ReliaTel only...
Страница 42: ...T_C IOM 2A 42...
Страница 43: ...43 T_C IOM 2A...