Appendix B- Request for Initial Startup
80
ARTC-SVX002A-EN
Initial Start-up Agreement
By signing this form, you agree the chiller is ready for initial startup. It is understood that, if the chiller is not ready for initial
startup due to site problems, the initial startup will be aborted at the discretion of the designated start-up technician.
Payment for an aborted startup will be forfeited. Rescheduled initial startups are subject to any additional costs that may
have been incurred by the technician. An approved purchase order or payment in advance will be required to reschedule
an aborted initial startup.
Name (Printed): ____________________________________ Date: ________________________
Signature: ___________________________ Company __________________________________