Installation
An additional 1-1/4” non-connectable water drain is located in the base rail within the heating
section.
Ensure that all condensate drain line installations comply with applicable building and waste
disposal codes.
Removing Supply and Exhaust/Return Fan Shipping Channels (Motors >5Hp)
Each supply fan assembly and exhaust fan assembly for S_HL units shipped with a motor larger
than 5 HP is equipped with rubber isolators (as standard) or optional spring isolators. Each return
fan assembly for S_HL units shipped with a motor larger than 5 HP is equipped with spring
isolators. Shipping channels are installed beneath each fan assembly and must be removed. To
locate and remove these channels, refer to
, and use the following
procedures:
Rubber Isolators:
1.
Remove and discard the shipping bolts from the fan assembly rails.
2. Elevate the fan-and-motor assembly and slide the shipping channels out from between the fan
assembly rails and the unit's base rail.
3. Lower the fan-and-motor assembly onto the isolators. Make sure that the pins at the top of the
isolators are engaged in the corresponding holes on the fan assembly.
4. Verify that the fan assembly is being supported by the isolators.
Spring Isolators:
See
and
for spring isolator locations.
1.
Remove and discard the shipping tie down bolts.
2. Remove the shipping channels and discard.
Note:
Fan assemblies not equipped with rubber or spring isolators have mounting bolts at the
same locations and must not be removed.
Note:
If return fan backside spring isolator repair/replacement is required, access the backside of
the return fan by entering the unit filter section. Remove the top pivot bearings from the
three fixed- position return damper blades (bolted together as a single section with an angle
brace). Lift the three-blade section as a single unit from the return damper assembly and set
aside or lean in against the return fan frame. Then enter the return fan compartment from
the filter section to perform service work on the rear isolators.
Figure 19. Condensate Trap Installation
L
G
Содержание IntelliPak SAHL Series
Страница 47: ...RT SVX36G EN 47 Installation Figure 16 Unit rigging Figure 17 Typical unit base and roof curb cross section...
Страница 65: ...RT SVX36G EN 65 Installation Figure 30 Hot Water Piping 90 130 Ton Figure 31 Steam Coil Piping 20 36 Ton...
Страница 86: ...86 RT SVX36G EN Installation Figure 38 Field connection diagram notes for 20 89 ton CV or VAV applications...
Страница 87: ...RT SVX36G EN 87 Installation Figure 39 Typical field wiring diagram for 20 89 ton VAV control option 2307 9177...
Страница 88: ...88 RT SVX36G EN Installation Figure 40 Typical field wiring diagram for 20 89 ton VAV control option...
Страница 173: ...RT SVX36G EN 173 Startup Checklists Figure 88 Dry bulb changeover map...
Страница 175: ...RT SVX36G EN 175 Maintenance Figure 89 Unit internal fuse replacement data for air handling units...