Unit Rigging & Placement
Note:
Use spreader bars as shown in the diagram. Refer to the Installation manual or nameplate
for the unit weight. Refer to the Installation Instructions located inside the side control panel
for further rigging information.
1.
A Center-of-Gravity illustration and the dimensional data is shown in
.
2. Attach adequate strength lifting slings to all four lifting lugs on 20 through 75 Ton units. The
minimum distance between the lifting hook and the top of the unit should be 7 feet for 20
through 75 Ton units.
illustrates the installation of spreader bars to protect the
unit and to facilitate a uniform lift.
lists the typical unit operating weights.
3. Test-lift the unit to ensure it is properly rigged and balanced, make any necessary rigging
adjustments.
4. Lift the unit and position it over the curb and pedestal. (These units have a continuous base rail
around the air handler section which matches the curb.
5. Align the base rail of the unit’s air handler section with the curb rail while lowering the unit onto
the curb. Make sure that the gasket on the curb is not damaged while positioning the unit. (The
pedestal simply supports the unit’s condenser section)
A cross section of the juncture between the unit and the roof curb is shown in
.
Figure 15. Solid flow baffle wall installation for non-Trane roof curbs
Return Fan
Roof Curb
Return Airflow
Flow Baffle
Return Airflow
Duct
WARNING
Heavy Objects!
Ensure that all the lifting equipment used is properly rated for the weight of the unit being
lifted. Each of the cables (chains or slings), hooks, and shackles used to lift the unit must be
capable of supporting the entire weight of the unit. Lifting cables (chains or slings) may not be
of the same length. Adjust as necessary for even unit lift. Other lifting arrangements could
cause equipment or property damage. Failure to follow instructions above or properly lift unit
could result in unit dropping and possibly crushing operator/technician which could result in
death or serious injury.
Содержание IntelliPak SAHL Series
Страница 47: ...RT SVX36G EN 47 Installation Figure 16 Unit rigging Figure 17 Typical unit base and roof curb cross section...
Страница 65: ...RT SVX36G EN 65 Installation Figure 30 Hot Water Piping 90 130 Ton Figure 31 Steam Coil Piping 20 36 Ton...
Страница 86: ...86 RT SVX36G EN Installation Figure 38 Field connection diagram notes for 20 89 ton CV or VAV applications...
Страница 87: ...RT SVX36G EN 87 Installation Figure 39 Typical field wiring diagram for 20 89 ton VAV control option 2307 9177...
Страница 88: ...88 RT SVX36G EN Installation Figure 40 Typical field wiring diagram for 20 89 ton VAV control option...
Страница 173: ...RT SVX36G EN 173 Startup Checklists Figure 88 Dry bulb changeover map...
Страница 175: ...RT SVX36G EN 175 Maintenance Figure 89 Unit internal fuse replacement data for air handling units...