Startup Checklists
24-89 Ton — Evaporative Condenser
Important:
Water treatment is required before beginning startup. Failure to do so will damage
the unit and result in premature unit degradation.
This checklist is intended to be a guide for the start up technician. Many of the recommended checks
and actions could expose the technician to electrical and mechanical hazards. Refer to the
appropriate sections in the unit IOM for appropriate procedures, component specifications and
safety instructions.
Important:
This checklist is not intended to be a substitution for the contractors installation
instruction.
Table 54. Critical control parameters
Notes:
1.
Using the Human Interface (HI), go to SETUP Menu and input setting for parameters listed below.
2.
Use the map shown below to determine region of country based on unit site location.
Suggested
Parameter
Economizer Settings
Region 1 Region 2 Region 3 Region 4 Region 5 Region 6 Region 7
Supply Air Temperature Control Setpoint
8°F
Supply Air Temperature Deadband
55°F
Supply Air Pressure Setpoint
1.8" w.c.
Supply Air Pressure Deadband
0.1" w.c.
Building Static Pressure Setpoint
0.03" w.c.
Building Static Pressure Deadband
0.04" w.c.
Standby Freeze Avoidance
20%
Exhaust Enable Setpoint
10%
Economizer Minimum Position Setpoint
10%
Fixed Dry Bulb Economizer C/O
Type a (Moist)*
T
OA
> 65°F T
OA
> 65°F T
OA
> 65°F T
OA
> 65°F T
OA
> 70°F T
OA
> 70°F T
OA
> 70°F
Fixed Dry Bulb Economizer C/O
Type b (Dry)*
T
OA
> 75°F
Fixed Dry Bulb Economizer C/O
Type c (Marine)*
T
OA
> 75°F T
OA
> 75°F T
OA
> 75°F
Fixed Reference
Enthalpy Changeover
H
OA
> 28 Btu
Differential Comparative
Enthalpy Changeover
H
OA
> H
RA
Note:
) below for dry bulb changeover.
Examples:
(a) Minneapolis, Minnesota is in “Region 6" and resides in “Moist” subregion, thus designation is 6b. Economizer changeover setting
should be 75°F.
(b) Charleston, South Carolina is in “Region 3" and resides in “Moist” subregion, thus the designation is 3c. Economizer changeover setting
should be 65°F.
Job Name
Serial #
Job Location
Model #
Sales Order #
Ship Date
Unit DL # (special units)
Date
Starting Sales Office
Technician
Содержание IntelliPak SAHL Series
Страница 47: ...RT SVX36G EN 47 Installation Figure 16 Unit rigging Figure 17 Typical unit base and roof curb cross section...
Страница 65: ...RT SVX36G EN 65 Installation Figure 30 Hot Water Piping 90 130 Ton Figure 31 Steam Coil Piping 20 36 Ton...
Страница 86: ...86 RT SVX36G EN Installation Figure 38 Field connection diagram notes for 20 89 ton CV or VAV applications...
Страница 87: ...RT SVX36G EN 87 Installation Figure 39 Typical field wiring diagram for 20 89 ton VAV control option 2307 9177...
Страница 88: ...88 RT SVX36G EN Installation Figure 40 Typical field wiring diagram for 20 89 ton VAV control option...
Страница 173: ...RT SVX36G EN 173 Startup Checklists Figure 88 Dry bulb changeover map...
Страница 175: ...RT SVX36G EN 175 Maintenance Figure 89 Unit internal fuse replacement data for air handling units...