Unit Start Up
To remove shipping brackets
Important:
Remove fan shipping brackets before startup. Failure to remove brackets could result
in fan damage.
Evaporative condensers are shipped with fan shipping brackets to reduce damage caused by
vibration during shipment. The fan shipping brackets must be removed prior to unit startup.
To remove the shipping brackets start from the side opposite to the drain actuator:
1.
Loosen the screw for the bracket that holds the inlet louvers below the door side.
2. Remove inlet louvers and set to the side.
Note:
Service technician may need to step on the horizontal surface of FRP coated base.
Step with care.
3. Unscrew the bolt in the middle of the door. Keep the bolt in a safe place.
4. Lift one door with handle until it touches the top. Swivel bottom of door to remove it from the
door opening and set it to the side.
5. Slide and remove the middle mist eliminator section so that the shipping bracket is visible.
6. Use screw gun to unscrew the two screws that hold the fan shipping bracket. The bracket should
drop down but still remain engaged with a hook on the bracket.
7.
Go to the other side of the unit and follow the procedure for inlet louver and door removal
(see steps 1 - 6).
8. Hold the bracket with one hand and remove remaining two screws.
9. Remove the bracket and all the removed screws from the unit.
Important:
Make sure there are no screws remaining in the coil area.
10. Reinstall inlet louvers, mist eliminators and louvers.
11. Check that the direction of arrow on the inlet louver is correct.
Содержание IntelliPak SAHL Series
Страница 47: ...RT SVX36G EN 47 Installation Figure 16 Unit rigging Figure 17 Typical unit base and roof curb cross section...
Страница 65: ...RT SVX36G EN 65 Installation Figure 30 Hot Water Piping 90 130 Ton Figure 31 Steam Coil Piping 20 36 Ton...
Страница 86: ...86 RT SVX36G EN Installation Figure 38 Field connection diagram notes for 20 89 ton CV or VAV applications...
Страница 87: ...RT SVX36G EN 87 Installation Figure 39 Typical field wiring diagram for 20 89 ton VAV control option 2307 9177...
Страница 88: ...88 RT SVX36G EN Installation Figure 40 Typical field wiring diagram for 20 89 ton VAV control option...
Страница 173: ...RT SVX36G EN 173 Startup Checklists Figure 88 Dry bulb changeover map...
Страница 175: ...RT SVX36G EN 175 Maintenance Figure 89 Unit internal fuse replacement data for air handling units...