Installation Checklist
The following checklist is provided as an
abbreviated guide to the detailed installation
procedures given in this manual. This list
should be used by the installer to ensure that
all necessary procedures have been
completed. For more complete information,
refer to the appropriate sections in this
manual.
WARNING: Disconnect electrical power
source and secure in disconnected
position before servicing the unit. Failure
to do so may result in personal injury or
death from electrical shock.
•
Units are checked for shipping damage.
•
Unit location is prepared for weight,
leveling and service access.
•
Unit is mounted securely to the ceiling
support rods.
•
Ductwork connections are complete.
•
Coil connections are complete and tight.
•
Condensate drain pan connections are
complete and tight.
•
Electrical connections completed (fan
switches, thermostats, heaters).
•
Ground connection completed. Unit casing
is level. Motor-blower assembly rotates
freely.
•
Debris on the fan wheel and drain pan are
cleared.
•
Start-up preparation is complete and unit is
in the proper operating mode.
•
Owner-operator is instructed on unit
operation.
CAUTION: Use only copper conductors
for wiring connections. Unit terminals are
not designed to accept other types of
wiring. Aluminum or other conductors
may cause overheating and unit damage.
11
HFCF-SVX01A-EN
Содержание HFCF-SVX01A-EN
Страница 1: ...Installation Operation Maintenance Chilled Water Fan Coil Unit Airflow 200 1400CFM HFCF SVX01A EN...
Страница 8: ...Dimension Data and Weights Figure 2 Typical Installation Figure 3 Duct Work 8...
Страница 10: ...Wiring Diagram Figure 7 Model HFCF Wiring Diagrams 10...
Страница 13: ...Figure 8 Fan Board Assembly Maintenance...