V07-19.0
19/115
Figure 7:
Crane lug dismounted
Figure 8:
Crane lug mounted
Bolts and nuts are delivered with the lifting lugs and must be tightened with the torque according to
. If the lifting lugs are already mounted by TRANE, the bolts must be checked before lifting
of the AHU.
Figure 9
: Base frame height
Base frame height H (mm)
Bolt type
Nm
80
M8x20
10
Table 2:
Tightening torque for bolts
3.3.3
Lifting of CCE Compact AHU by crane lugs
-
The load effect has to take place uniformly across all four crane lugs.
-
The definition of the load carrying equipment is the responsibility of the executing company.
-
The correct guidance of the load carrying equipment according to
-
After the pre-positioning of the delivery section at the desired position, remove the lifting lugs
and use them for the next delivery section.
Base frame height
Содержание CCE-Compact Series
Страница 1: ...July 2019 AH SVX007A GB Installation Operation Maintenance CCE Compact Air Handling Unit...
Страница 60: ...60 115 V07 19 0 User manual COMPACT V0 03 April 2018 Hotline 39 335 1334212...
Страница 92: ...92 115 V07 19 0 Data point list COMPACT V0 06 April 2018 Hotline 39 335 1334212...