background image

 

Page 25

Installer’s Guide

Service Maintenance

Service maintenance should be performed by qualified service 

personnel. 

Cooling Season

To keep the unit operating safely and efficiently, the manufacturer 

recommends that a qualified service technician check the entire 

system at least once each season or more often if needed. The 

service technician should examine these areas of the 4YCZ6 unit:

 

filters (for cleaning or replacement)

  motors and drive system components (for proper operation)

 

economizer gaskets (for possible replacement)

 

safety controls (for mechanical cleaning)

 

electrical components and wiring (for possible replacement 

and connection tightness)

 

condensate drain (for proper sealing and cleaning)

 

unit duct connections (to see that they are physically sound 

and sealed to the unit casing)

 

unit mounting support (for structural integrity)

 

the unit (for obvious unit deterioration)

Heating Season

Complete the following unit inspections and service routines 

described at the beginning of each heating season.

 

Visually inspect the unit to ensure that the airflow required 

for combustion and condenser coil is not obstructed from the 

unit.

 

Inspect the control panel wiring to verify that all electrical 

connections are tight and that the wire insulation is intact.

 

Check the operation of the gas ignition system as follows: 

Turn off the gas supply with the unit operating to verify that 

the gas valve closes and that a re-ignition cycle is initiated 

by the unit. 

 

Visually inspect the inside of the burners and the burner ports 

for deposit buildup and corrosion.  Wipe and brush the inside 

of the burner and the burner ports and then clean with a dry 

cloth.  If the deposit buildup or corrosion is excessive, replace 

the burners.

Flue Hood and Combustion Blower Cleaning

Manifold Pressure Check and Adjust

 

1. Connect a manometer to the pressure tap at the outlet side 

of the unit’s gas valve (remove the Control/Heat access 
panel).  Read the manifold pressure with the burners firing. 
See Figure 16 on page 17 for gas valve connections.

  2. If the manifold pressure reading does not match the value 

indicated on the unit's nameplate, the unit's pressure regula-
tor must be adjusted as follows:

 

a. Remove the cover screw on the gas regulator located on 

the front side of the unit’s gas valve.

 

b. Turn the adjusting screw clockwise to increase manifold 

pressure or counterclockwise to decrease manifold pres-
sure.

  3.  Check the temperature rise during furnace operation to insure 

that it falls within the range specified on the unit's nameplate.

  4.  If the temperature rise noted is outside of the specified limits, 

adjust the indoor air flow to cause the temperature rise of 
the heat exchanger to fall within the required range.

CAUTION

!

Never use combustible cleaning fluids on any part of the 

furnace.

Before each heating season, the Flue Hood and combustion 
blower should be inspected for signs of any blockage or soot-
ing. 

Any cleaning required should be performed only by a 

qualified service technician

 using the following procedure:

1.  Turn the comfort control to OFF. Turn off power to the unit. 

Turn the main power disconnect OFF. Turn the manual gas 
valve OFF.

2.  Remove the Flue Hood from the side panel.
3.  Remove the combustion blower from the vestibule panel. 

Disconnect blower wiring and pressure switch hose.

4.  Wipe blower and Flue Hood clean with a dry cloth. 
5.  Replace the combustion blower gasket with a new one.
6.  Reassemble combustion blower and Flue Hood in reverse 

order of removal. Reconnect pressure switch hose.

7.  Verify all wiring is correct per the unit's wiring diagram.
8.  Follow start-up procedure to place unit back in service. Verify 

proper operation.

Содержание 4YCZ6024

Страница 1: ...ures on the fan Operating the unit without the access panels properly installed may result in severe personal injury or death WARNING SAFETY HAZARD This information is for use by individuals having adequate backgrounds of electrical and mechanical experience Any attempttorepairacentralairconditioningproductmayresult inpersonalinjuryand orpropertydamage Themanufacturer or seller cannot be responsib...

Страница 2: ...R 410A operating pressure exceeds the limit of R 22 Proper service equipment is required Failure to use proper service tools may result in equipment damage or personal injury SERVICE Use only R 410A Refrigerant and approved POE compres sor oil IMPORTANT Wear appropriate gloves arm sleeve protectors and eye protection when servicing or maintaining this equipment PRECAUTIONARY MEASURES Avoid breathi...

Страница 3: ...g 16 Gas Piping Installation 16 Pipe Delivery Schedule natural gas only 17 Gas Pressure Set up Precautions 17 Gas Supply Line Pressure all fuels 17 Verify Manifold Pressure 18 Input Check and Adjustment 18 High Altitude Installation 19 Air Filter Installation 19 Electrical Wiring 19 Electrical Connections 18 Electrical Power 19 Disconnect Switch 19 Over current Protection 19 Power Wiring 19 Contro...

Страница 4: ... Determine Unit Clearances Figure 1 4YCZ6024 6036 1 of 3 Figures 1 through 6 show the unit critical dimensions DWG NO D673947G01_REVC NOTE The view labeled Bottom Side represents the Base as viewed looking up from underneath the unit ...

Страница 5: ...Page 5 Installer s Guide Figure 2 4YCZ6024 6036 2 of 3 ...

Страница 6: ...uide Step 2 Determine Unit Clearances Figure 1 4YCZ6024 6036 3 of 3 Figures 1 through 6 show the unit critical dimensions NOTE The view labeled Bottom Side represents the Base as viewed looking up from underneath the unit ...

Страница 7: ...Page 7 Installer s Guide Figure 4 4YCZ6048 through 4YCZ6060 1 of 3 NOTE The view labeled Bottom Side represents the Base as viewed looking up from underneath the unit ...

Страница 8: ...Page 8 Installer s Guide Figure 5 4YCZ6048 through 4YCZ6060 2 of 3 ...

Страница 9: ...Page 9 Installer s Guide Figure 6 4YCZ6048 through 4YCZ6060 3 of 3 ...

Страница 10: ...r to the Installation section for instruction on converting the supply and return airflow covers to down airflow 3 The field assembled Roof Mounting Curb BAYCURB050A or BAYCURB051A or a field fabricated curb should be in place before the unit is hoisted to the roof top The Roof Mounting Curb frame must be installed on a flat level section of the roof maximum of 1 4 per foot pitch and provide a lev...

Страница 11: ...clearance to combustible mate rial shall be maintained on air outlet duct Rooftop Installation Curb Mounting Convert Horizontal Airflow to Down Airflow The factory ships the unit for horizontal airflow Perform this procedure to convert the unit to down airflow 1 Remove the three 3 sheet metal screws securing the supply aircover and the four 4 sheet metal screws securing the return air cover from t...

Страница 12: ...tabs or flanges Failure to observe these warnings may result in equipment damage 1 Before preparing the unit for lifting check the unit dimension drawings for center of gravity for lifting safety Figures 1 to 6 page 4 9 Because of placement of internal components the unit s weight may be unevenly distributed Approximate unit weights are also provided in the unit drawings NOTE When unit rigging and...

Страница 13: ... roof top applications using field fabricated ducts and sleeper rails rather than a curb or frame use the following procedure 1 Locate and secure the sleeper rails to the roof Three 3 sleeper rails are required One on each end to support the edges of the unit and one across the center of the unit The center rail must run inside both drip lips Vibration isolators should be installed as indicated on...

Страница 14: ...sible for the unauthorized use of this drawing and expressly disclaims any liability for damages resulting from such unauthorized use Gasket Seal Spreader Bars Base of unit rest on top of curb rails Drip lip on perimeter of unit Top shipping skid attached to unit IMPORTANT To prevent damage to the sides and top of the unit when hoisting retain the top shipping skid on the unit or use spreader bars...

Страница 15: ...orizontal Airflow Application with Frame Supply Air Return Air Roof Flashing Channel Iron Center Support Center Sup port required on all Frame Applications Angle Iron Frame Roof Flashing Return Air Angle Iron Frame Roof Flashing Supply Air Channel Iron Center Support Center Support required on all Frame Applications ...

Страница 16: ...oise and vibration transmission Elbows with turning vanes or splitters are recommended to minimize air noise and resistance The first elbow in the ductwork leaving the unit should be no closer than two 2 feet from the unit to minimize noise and resistance To prevent leaking do not attach the ductwork to the bottom of the unit base refer to the bottom example in Figure 14 A 3 4 inch female NPT cond...

Страница 17: ...e making the gas pipe connection give serious consideration to providing the clearance necessary to remove the accesspanelsontheunit e g economizerandfilteraccesspanels NOTE In the absence of local codes the installation must con form with American National Standard Z223 1 National Fuel Gas Code Latest Revision The available gas supply must agree with the required gas supply marked on the unit nam...

Страница 18: ...nchonthegasvalveinletboss connect the gas piping to the unit Check the completed piping for leaks using a soap and water solution or the equivalent 6 After installation of the gas pipe in the unit the pipe opening should be closed with the filler barrier plug provided Manifold Pressure Check the manifold pressure at the unit gas valve Do not exceed the recommended pressure shown on the unit namepl...

Страница 19: ...hat require 49 orifices for altitudes from 7000 8000 orifices must be changed to 50 HIGH ALTITUDE DERATE CHART NAT Altitude In Feet Inputs shown are with factory orifices 3 5 WC High Fire 1 8 WC Low Fire Natural Gas heating value of 950 btu cuft Electrical Power It is important that proper electrical power be available for the unit Voltage variation should remain within the limits found on the uni...

Страница 20: ...itioning systems been checked at the service ports for charge and leak tested if necessary Does the condenser fan and indoor blower turn free without rub bing and are they tight on the shafts Has the indoor blower speed been determined and the proper speed been set See the Unit Wiring Diagram Has all work been done in accordance with applicable local and national codes Are all covers and access pa...

Страница 21: ...Page 21 Installer s Guide Figure 22 4YCZ6 Field Wiring Diagram NOTE For economizer wiring instructions see the Installer s Guide that came with your economizer ...

Страница 22: ...cooling setpoint to above room temperature Heating Cycle Theseunitsareequippedwithasolid stateignitioncontrolthatlights the burners each time the thermostat calls for heat The burners are extinguished during the OFF cycle The gas heating section of the unit can be started using the follow ing procedure 1 Be sure the thermostat is at its lowest setting and the power to the unit is off a Turn the ma...

Страница 23: ...ond postpurge The indoor blower motor will continue to operate at the current speed for 60 or 90 seconds after the flames are extinguished Sequence of Operation Safety Sequences This product is equipped with safety devices to protect against abnormal conditions The temperature limit switch TCO is located on the blower barrier andcanbeaccessedthroughtheblowercompartment Thisautomatic reset device p...

Страница 24: ... damage Do not store combustible materials gasoline or other flammable vapors or liquids near the unit WARNING Someoftheperiodicmaintenancefunctionsofthe4YCZ6unitcan beperformedbytheowner thisincludesreplacingthedisposable or cleaning the permanent air filters cleaning the unit cabinet and conducting a general unit inspection on a regular basis Filters When the system is in constant operation insp...

Страница 25: ... Hood and Combustion Blower Cleaning Manifold Pressure Check and Adjust 1 Connect a manometer to the pressure tap at the outlet side of the unit s gas valve remove the Control Heat access panel Read the manifold pressure with the burners firing See Figure 16 on page 17 for gas valve connections 2 If the manifold pressure reading does not match the value indicated on the unit s nameplate the unit s...

Страница 26: ... 3 Flashes Pressure switch problem detected Fast Flash Rate Not used 4 Flashes High Limit switch protection device open Steady ON Normal No Call for Heat 5 Flashes Flame sensed and gas valve not energized or flame sensed and no W signal 6 Flashes Flame Rollout Switch open 7 Flashes Thermostat miswired W1 W2 Fast Flash Rate The LED will flash on for 1 4 second and off for 1 4 second Slow Flash Rate...

Страница 27: ...Page 27 Installer s Guide ...

Страница 28: ...uide Trane 6200 Troup Highway Tyler TX 75707 9010 The manufacturer has a policy of continuous product and product data improvement and it reserves the right to change design and specification without notice 2017 Trane 09 18 ...