1. PREPARATIONS FOR INTRODUCING THE MACHINE
26
1.2.5
Marking on the Floor
(1) According to your floor plan specifying the lay-
out and spaces between machines, mark one
reference line lengthwise and one crosswise.
(2) According to the machine dimension drawing,
mark a front line, a rear line, and side lines for
the machine's feet parallel to the reference
lines marked in step (1).
NOTES:
•
If you have selected the gluing installation
method, only the front and side lines are
required.
•
For the loom dimensions, refer to the draw-
ing submitted from us.
1.2.6
Laying Anchor Bolts
(Only for
the bolting installation method)
For the straight-bolting installation method
(1) Positioning anchor bolts
Mark the positions of the anchor bolts accord-
ing to your floor plan (refer to floor plan exam-
ples given in pages 28 and 29). Make sure
that the bolt positions are within the tolerance
specified at left.
To obtain
l
3, use the following formula:
It is recommended that you use a gauge to
eliminate any positioning irregularities
between the weaving machines.
(2) Laying anchor bolts
1) According to the marks made in step (1), drill
anchor bolt holes with the dimensions shown
at left in the floor with a special drill.
After drilling, clean the inside of those holes by
blowing air into them.
l
3
l
1
2
l
2