1. PREPARATIONS FOR INTRODUCING THE MACHINE
22
1.2
Foundation Work
There are three types of installation methods for the
weaving machines:
•
Gluing installation
•
Bolting installation
•
On-the-floor installation
The bolting installation method may be divided into
either straight-bolting or L-bolting installation. This
manual describes the straight-bolting installation
method.
If Sikadure (explained later) is selected as the
bonding method, the steel packing is to be used for
leveling instead of felt packing.
1.2.1
Structure of Foundation
Build up the foundation of the weaving machine as
shown at left. The structure of the foundation is the
same for all of the gluing installation method, bolt-
ing installation method, and on-the-floor installation.
•
The pressure-withstanding strength of concrete
should be 26.5 MPa (270 kgf/cm
2
) or greater.
•
The details of the iron net are shown at left.
Straight-bolting Installation
Gluing Installation
Steel packing
Felt packing
Steel packing
The foundation will greatly influence the
degree of vibration which the machine will
cause.
For constructing the foundation, consult your
professional builder by referring to the draw-
ings submitted to you.
The compressive strength shall be measured
according to JIS A 1108 (Method of Test for
Compressive Strength of Concrete).
If any other standard is applied, check satis-
faction of the value specified in the JIS (Japa-
nese Industrial Standard) by converting the
measured value.
ATTENTION
ATTENTION