TORAY MBR
Instruction Manual
06-G-MB2-NHPAF-220801
28 of 63
Fig.IV-12 Riser Pipe (example)
Fig.IV-13 Separate Riser Pipe for Upper/Lower Decks (example)
Consider piping materials and regulate the load to the flange
connection points at less than 20 kg per flange in order to avoid
distortion, leakage, or breakage of the filtrate water manifold. If the
load exceeds the limit shown above, put some supports on the
piping to reduce the load.
Be sure to confirm that the diameter of filtrate piping is suitable for
the assumable maximum flow velocity at each point, especially
after aggregating filtrate flow from several manifolds such as
header pipes.
(3) Maximum Number of Modules in a Single Header
A maximum number of 30 modules per filtrate header with subgroups of max 10
modules for aeration (diffuser cleaning) and chemical cleaning is possible to design.
CAUTION
!
CAUTION
!