14
4.4
Hydraulic Plumbing
From this point on in the installation the booms will be inoperative until the
hydraulics are fully installed.
1.
After the NORAC valve is mounted, the hydraulic hoses and fittings can be plumbed. The
plumbing for the hydraulic circuit is shown schematically in
Figure 2.
2.
Install hoses H74 to the roll cylinder that was previously installed. Route the hoses to the
NORAC valve block.
3.
Connect the hose attached to the rod end of the cylinder to the “B” port of the expansion
block.
4.
Connect the hose attached to the cap end of the cylinder to the “A” port of the expansion
block.
Содержание NORAC UC4.5
Страница 1: ...Active Roll ControlTM Option Installation Manual...
Страница 5: ...2 2 Kit Parts 2 1 Kit Overview Figure 1 Roll Control Parts...
Страница 6: ...3 2 2 Hydraulic Plumbing Figure 2 Roll Control Hydraulic Plumbing...
Страница 11: ...8 Figure 7 Center Mark Location Centerline Mark 4 100mm...
Страница 21: ...18 8 Cable Drawings 8 1 ITEM C07 43220 0 5 CABLE UC5 NETWORK 14 AWG 0 5M...
Страница 22: ...19 8 2 ITEM C70 44658 46D CABLE UC4 VALVE DT ROLL WITH PIGTAIL...