ROAD BLOCKING SYSTEMS
Installation and Operation Manual
Revision 1.1 01.2022
Page
-
10
-
MECHANICAL TIRE-KILLER
Size
А4
ROAD BLOCKING SYSTEMS
Installation and Operation Manual
Revision 1.1 01.2022
Page
-
10
-
MECHANICAL TIRE-KILLER
Office and Production site: Tel.: +380 (44) 291-21-11
14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-02
E-mail: [email protected] www.tiso.global
џ
The road blocker to be installed by means of handling equipment;
џ
Safety regulations must be observed according to the applicable
standards during handling operations!
џ
Slinging must be performed by the qualified slingers having the
appropriate permit to work;
џ
Presence of unauthorized persons at the installation site during handling
operations is PROHIBITED!
6.
Road blocker installation
6.1 Arrangement of installation site:
џ
Arrangement of installation site must comply with requirements of the applicable
regulations and standards.
џ
Installation area shall be fenced along perimeter with temporary security fencing or
caution tape at the distance of 3 meters from the installation site.
џ
The appropriate warning signs ISO 7010: 2011 shall be installed in front of the installation
site.
џ
Make sure that there are no underground utilities at the installation site!
џ
Keep outsiders away from the installation site!
џ
Safety regulations must be observed during installation!
6.2 Installation procedure:
џ
Preparation of installation well (pit)
;
џ
Pit concreting;
џ
Installation of the road blocker in the predesign position
;
џ
Installation of the road blocker in the design position (for surface-mount type) and into
the pit (for submersible type);
6.3 Installation Technique:
6.3.1 Preparation of the surface-mount Tyre-Killer road blocker installation base:
1.The required marking according to the design solutions to be made;
2.The roadbed to be removed, if appropriate;
3.A pit with
А х B
dimensions and
C
depth to be dug (See Table 4);
4.50 mm sand cushion to be prepared;
5.Geotextile to be put on the pit bottom;
6.The pit to be filled with gravel (10-20mm grain size)at the height of 100mm;
7.150 mm concrete layer to be poured (Concrete С25/35 according to ENV-206) to the
roadbed level;
8.Horizontal position to be checked with builder's level;
9.The road bloker to be installed in the design position*.