![TIGIEFFE AIRO R Series Скачать руководство пользователя страница 72](http://html1.mh-extra.com/html/tigieffe/airo-r-series/airo-r-series_use-and-maintenance-manual_1115901072.webp)
Use and Maintenance Manual - R13 R17 Series
Page 72
7.2.9.
Inclinometer operation check
WARNING!
Usually the inclinometer does not need to be adjusted unless the electronic control unit is replaced. The
equipment necessary for the replacement and adjustment of this component is such that these operations
should be carried out by skilled personnel.
AS THIS OPERATION IS VERY IMPORTANT IT IS TO BE CARRIED OUT BY SKILLED TECHNICIANS ONLY.
The inclinometer does not require any adjustment since it is
calibrated in the factory before the machine is delivered.
This device controls the chassis inclination and when
inclined over the allowed value:
it inhibits lifting and telescopic extension;
It warns of the instability condition by means of an
audible alarm and a warning light located on the
platform (see “General use instructions”).
lowering, telescopic retraction, turret rotations are
possible. All at an automatically reduced speed.
The inclinometer checks the inclination with respect to the
two axes (X; Y). On machine models that have the same
transversal and longitudinal inclination limits, the control is
carried out with reference to one axis only (X-axis).
Check operation at least once a year.
Fig. 32
To check the inclinometer operation according to the
longitudinal axis (generally X-axis):
place 2 shims (A+10mm, see following table) under the 2 front or rear outriggers.
Wait three seconds (operation delay set at factory) until the danger red light and the platform audible alarm turn on.
make sure the lifting and telescopic boom extension controls are inhibited;
if platform is lifted make sure the lowering and cage rotation controls are available; all at an automatically reduced speed.
To check the inclinometer according to the transversal axis (normally Y-axis):
place 2 shims (B+10mm, see following table) under the 2 right or left outriggers.
Wait three seconds (operation delay set at factory) until the danger red light and the platform audible alarm turn on.
make sure the lifting and telescopic boom extension controls are inhibited;
if platform is lifted make sure the lowering and cage rotation controls are available; all at an automatically reduced speed.
MODELS
SHIMS
R13
R17
A [mm]
26
26
B [mm]
26
26
WARNING! The dimensions of shims A and B refer to max. allowed inclination as indicated in table
“TECHNICAL FEATURES”. To be used during the inclinometer calibration.
Содержание AIRO R Series
Страница 16: ...Use and Maintenance Manual R13 R17 Series Page 16 Fig 3...
Страница 21: ...Use and Maintenance Manual R13 R17 Series Page 21 Fig 4...
Страница 81: ...Use and Maintenance Manual R13 R17 Series Page 81...
Страница 98: ...Use and Maintenance Manual R13 R17 Series Page 98...
Страница 99: ...Use and Maintenance Manual R13 R17 Series Page 99 12 WIRING DIAGRAM 043 08 001...
Страница 100: ...Use and Maintenance Manual R13 R17 Series Page 100 043 08 002...
Страница 101: ...Use and Maintenance Manual R13 R17 Series Page 101...
Страница 102: ...Use and Maintenance Manual R13 R17 Series Page 102 CE Connector 9 10 11 and 12 free CE connector 9 10 11 and 12 free...
Страница 103: ...Use and Maintenance Manual R13 R17 Series Page 103 059 08 005 CA1...
Страница 104: ...Use and Maintenance Manual R13 R17 Series Page 104 059 08 007 CR...
Страница 105: ...Use and Maintenance Manual R13 R17 Series Page 105 059 08 001...
Страница 106: ...Use and Maintenance Manual R13 R17 Series Page 106 059 08 006...
Страница 107: ...Use and Maintenance Manual R13 R17 Series Page 107...
Страница 108: ...Use and Maintenance Manual R13 R17 Series Page 108 043 08 017...
Страница 109: ...Use and Maintenance Manual R13 R17 Series Page 109 059 08 012...