Unit Installation
Before installing the ALPS30 unit, verify that the delivery is complete and that the
unit and any accessory parts are intact and free from any signs of transportation
damage. Ensure that all external and internal packaging has been removed from
the unit before installation.
NOTE
Please retain all packaging for future transportation and storage of the
unit and its accessories.
The ALPS30 unit should be installed in a location which meets the following
requirements:
•
Safe and suitable operating environment (see
)
•
Solid, stable, and level working surface
•
At least 4 in. (10 cm) clearance around the unit to adjacent objects and
walls
•
Grounded AC mains power connection (see
)
WARNING
Please observe and abide by the Unit Installation and Operating
Environment safety precautions and preconditions listed in
Precautions and Limitations of Use
section.
It is important to check that the MAINS VOLTAGE SELECTOR SWITCH on the rear
of the unit is set to the correct position for the desired operating voltage, and that
the correct fuse type is fitted in the FUSE HOLDER (see