Make marks for the holes on the wall (with en-closed drill
template/base).
Drill holes.
Ø 6 mm
60mm
Feed cable through the seal of the base.
Fasten base (and spacer frame) to the wall.
OR
brown
brown
Phase
Switched
phase
Neutral
conductor
Neutral
conductor
Earthing
conductor
Earthing
conductor
blue
blue
green/yellow
Connect the individual wires to the appropriate terminal.
Tighten screws.
Click!
Click!
Plug motion detector into base and click in.
Connect motion detector to power supply.
Dismantling
Using the screwdriver, carefully loosen the snap-in hook at
the side and pull the device forward.
Installation instructions
As the detector reacts to variations in temperature, avoid the
following situations:
Do not direct motion detectors at objects with highly reflec-
tive surfaces such as mirrors etc.
Do not install motion detectors near heat sources such as
heating outlets, air conditioning systems, lamps etc.
Do not direct the motion detector at objects that turn in the
wind such as curtains, large plants etc.
Take account of motion direction during test run.
10
20
30
40
40
10
20
30
40
40
10
20
30
40
40
5 m
16 m
360°
•
Recommended installation height: 2 – 4 m
•
Crosswise detection area: 16 m (crosswise to the detector)
•
Frontal detection area: 5 m (in front of the detector)
•
Detection angle: 360°
5. Direction test and alignment
The walk test is used to test the detection range and to res-
trict it if necessary.
Set the potentiometer time (min) to test.
The motion detector now only reacts to movement (indepen-
dent of brightness).
Crosswise to the detection area. After the motion detector
has detected a movement, it switches on for 2 s.
Note direction of motion during the test.