Standard Operating Procedures 7
Operations Manual
Bison 120
20-07-2018
Page 7-15
Revision 2.0
7.7 Shutdown
At the end of operation for the day it is recommended that the machine is routinely cleaned down
and checked for damage. It must also be checked for wear or leaks and fixed before further
operation.
In an emergency situation the emergency stops can be activated to stop the machine. If it happens,
all the material needs cleared from the machine before it can be started again.
The machine must not be shut down at the end of a working shift by only switching off the engine,
all components must be shut down in the correct sequence prior to this.
Before stopping the machine ensure that all components are clear of material.
When the engine of the crusher is stopped, it will continue to rotate for approximately 30 seconds
under the inertia effect of the flywheels. Pay careful attention before carrying out any work inside
the crusher or the machine and wait until the crusher is completely still.
PROCEDURE
1. Ensure that all material has passed through the chamber and has been discharged.
2. While the machine is operating rotate the speed regulator (Item 2) anti-clockwise to completely
stop the vibrating drawer.
.
Figure 7.15 - Vibrating Drawer Regulator
3. Pull the engine ignition switch (Item 2) to stop the engine, Reference: Figure 7.16.
Figure 7.16 - Ignition Toggle Switch
4. When the machine has completely stopped turn the ignition key to the off position and
remove the key.
Содержание Evoquip Bison 120
Страница 2: ...EvoQuip 200 Coalisland Road Dungannon Co Tyrone BT71 4DR Telephone 44 0 28 8774 0701...
Страница 23: ...Operations Manual Bison 120 20 07 2018 Page 2 7 Revision 2 0 Safety 2 Figure 2 1 Location of Safety Signs...
Страница 36: ...2 Safety Operations Manual Bison 120 20 07 2018 Page 2 20 Revision 2 0 Intentionally Left Blank...
Страница 42: ...3 Technical Data Operations Manual Bison 120 20 07 2018 Page 3 6 Revision 2 0 Intentionally Left Blank...
Страница 102: ...7 Standard Operating Procedures Operations Manual Bison 120 20 07 2018 Page 7 20 Revision 2 0 Intentioanlly Left Blank...
Страница 116: ...9 Maintenance Operations Manual Bison 120 20 07 2018 Page 9 8 Revision 2 0 Figure 9 2 Grease Points Cont...
Страница 196: ...10 Troubleshooting Operations Manual Bison 120 20 07 2018 Page 10 22 Revision 2 0 Intentionally Left Blank...
Страница 197: ...Storage 11 Operations Manual Bison 120 20 07 2018 Page 11 1 Revision 2 0 Table of Content 11 Storage 11 2...
Страница 204: ...Operations Manual Bison 120 20 07 2018 Page 12 6 Revision 2 0 12 Glossary of Terms Intentionally Left Blank...
Страница 206: ...Appendix Operations Manual Bison 120 20 07 2018 Page 13 2 Revision 2 0 Intentionally Left Blank...
Страница 208: ...Appendix A Operations Manual Bison 120 20 07 2018 Page A 2 Revision 2 0...
Страница 214: ...Appendix B Operations Manual Bison 120 20 07 2018 Page B 6 Revision 2 0 Intentionally Left Blank...
Страница 216: ...Appendix C Operations Manual Bison 120 20 07 2018 Page C 2 Revision 2 0 Intentionally Left Blank...
Страница 218: ...Appendix C Operations Manual Bison 120 20 07 2018 Page C 4 Revision 2 0 b Front Panel CPU Connection Cont...
Страница 219: ...Appendix C Operations Manual Bison 120 20 07 2018 Page C 5 Revision 2 0 c Main Wiring...
Страница 220: ...Appendix C Operations Manual Bison 120 20 07 2018 Page C 6 Revision 2 0 d Relay Box...
Страница 223: ......