TemperZone OPA 1370RKTM01 Скачать руководство пользователя страница 1

OPA 1370RKTM01
Packaged Reverse Cycle R410A

Air Cooled Air Conditioner

GENERAL

This OPA 1370RKTM Outdoor Unit must be 

installed in accordance with all national and 

local safety codes.

REFRIGERATION SYSTEM

General

The OPA 1370 has four independent 

refrigeration circuits and four compressors 

to provide the flexibility and economy of 

two stage operation, i.e. utilising one or 

two circuits as conditions vary, plus the 

advantage of staggered starting.
Each refrigeration system has been 

charged with HFC-410A (R410A) 

refrigerant; refer wiring diagram 

specification table for amount. Tapping 

points are provided to measure discharge 

and suction operating pressures.  

Compressors

The compressors are directional scroll 

type. The compressor lubricant is polyol 

ester oil (POE). Note, this oil absorbs 

moisture quickly if exposed to open air. 

On commissioning, the compressors must 

be checked for correct rotation (refer Start 

Up Procedure). A time delay prevents 

simultaneous starting of the compressors.

ECONOMISER (Option)

If the outdoor air temperature or heat 

content preferably, is below that of the 

return air the fresh air damper opens and 

the return air damper closes to provide the 

first stage of cooling. A spill air facility in the 

building may be necessary for when the 

return air damper is closed. The fresh air 

damper should return to minimum setting 

and the return air damper open before 

compressors are allowed to operate to 

provide further cooling.  

INSTALLATION
Positioning

Refer to dimension diagrams for minimum 

clearances. If multiple units are to be 

placed side-by-side then allow at least 2 m 

between coil faces.

Mounting

The unit should be fastened to a firm flat 

horizontal base using the holes supplied in 

the mounting channels.
When the unit is being installed on a roof 

it is recommended that the unit is installed 

on a substantial structure with vibration 

isolating mounts or pads beneath the unit. 
Flexible duct connections are 

recommended between the supply and 

return ducts and the unit.

Installation & 

Maintenance

Condensate Drain

The condensate drain should be 'U' trapped 

outside the unit. The trap should have a 

vertical height of at least 100 mm. The drain 

should have a slope of at least 1 in 50 and 

must not be piped to a level above the unit 

drain pipe.

Electrical Requirements

Electrical work must be done by a qualified 

electrician.  The outdoor unit must be wired 

directly from a distribution board by means 

of a circuit breaker or H.R.C. fuse, and a 

mains isolator provided - preferably close to 

the unit.

Note:  DO NOT USE REWIRABLE FUSES.
The OPA 1370 is provided with a 24V AC 

control circuit for a thermostat, on/off switch 

and/or time clock.
The control transformer 240V primary 

voltage is used for countries with 230-240V 

power supply. For countries with supply 

voltages 200-220V, change the primary 

voltage on the transformer to 208V.
Standard units are suitable for use with 

thermostats with either manual Heat/Cool 

selection or automatic changeover subject to 

the contact ratings of the thermostats. 
A 24 hour power supply to the control circuit 

is required, otherwise the warranty is void.

CHECK TESTS

1.  Check that all the shipping bolts on the 

back of the compressor frame have been 

removed and that the compressor is 

secure on its mounts.

2.  Check by hand that all fan motors can 

turn freely. 

3.  Check that the air filters have been 

correctly installed, if fitted.

4.  Check air diffuser dampers are open if 

appropriate.

5.  Check that the thermostat, or external 

24V controller, is correctly wired to the 

unit and is set at the desired temperature.

6.  Check the tightness of all electrical 

connections.

7.  Leave the thermostat, or external 24V 

controller, in the off position and close the 

mains isolating switch. (A four hour delay 

period is required to allow the crankcase 

heater to drive any liquid refrigerant out of 

the compressor oil.)

8.  Check the supply voltage between each 

phase and neutral. 

START UP PROCEDURE

After the four hour delay for the crankcase 

heater has expired, use the supplied 

Commissioning Sheet (Form NS 228) to 

record results when completing the following 

‘Start-up’ procedure. A UC6 Service 

Interface tool is supplied to read, pressures, 

superheat and its set-point, compressor 

amps etc.

1.  Select a sensible Fan speed (or Auto 

Fan mode), operating cycle (cool or 

heat), and room temperature set point, 

depending on the time of year, such that 

the compressor will start and run at a 

high capacity.

2.  Turn ON the thermostat / external 

controller. Wait for the compressor to 

start. Measure the current for each 

phase feeding into the compressor’s.

Compare against the compressor amps 

specified on the unit’s wiring diagram. 

3.  Compressors fitted are directional. 

Check for correct rotation. If rotation is 

incorrect the compressor will not pump, 

be noisy, and will draw minimal current. 

To correct motor rotation, change the 

phasing at the main power terminal. If 

changing the phasing, check the indoor 

air fan then runs in the correct direction 

also.

4.  Measure the current draw of each fan 

motor. Check all readings against the 

specified values in the wiring diagram.

5.  Use the UC6 Service Interface tool  to 

check operating pressures and status. 

If the UC6 Service Interface is not 

available, fit gauges and measure the 

suction and discharge pressures of both 

refrigeration circuits. 

6.  Check that the outdoor air fan motors are 

running smoothly and drawing less than 

the full load amps specified.

7. Check the indoor unit's fan belt tension 

after 20 mins of operation and adjust if 

necessary (refer Commissioning Sheet).

8.  Test the operation of the reversing valve 

by running the unit in both the heating 

and cooling mode.

9.  Check the supply air flow at each outlet.

10. Touch up any outdoor unit paintwork 

damage to prevent corrosion.

SETTING SUPPLY AIR FLOW

Consult OPA 1370 Technical Data pamphlet 

for details of airflow/duct static pressure, if 

required. 
If the indoor air returning to the unit is 

regularly expected to be above 50%RH, 

OPEN

DRAIN

MINIMUM

SLOPE

20 mm PER m

(1 IN 50)

100 mm

MINIMUM

200 mm

APPROX.

'U' TRAP

100 mm

APPROX.

VENT PIPE

FOR LONG

CONDENSATE

DRAIN RUNS

Отзывы: