1.

INTRODUCTION

The Taylex

 

ABS

42

00 Secondary Treatment System is designed to be installed both in- 

ground and abov

e

 ground, collecting all wastewater from a domestic residence or

 

suitable commercial properties. This manual has been put together to explain the

 

installation process of the ABS

42

00 system as a guide only. Some sites may differ in

 

access and slope, which need to be taken into account when delivering and installing the

 

system

.

2.

SAFETY   INSTRUCTIONS

Follow all safety instruction provided by the onsite builder and ensure you 

have all the relevant licences to perform this work.

 

Ensure the correct measurements are in place to prevent the 

general public from entering the site during the installation of the 

ABS

42

00.

 

Excavated holes should be fenced if the ABS

42

00 is not 

immediately installed.

 

SLIPPERY WHEN WET!

 

During cleaning, maintenance & repair work, the surrounding area may 

become extremely slippery due to spilt water. Caution is to be taken 

when walking/standing near the ABS

42

00 when these activities are 

being conducted.

 

Use safe lifting techniques when installing/relocating the ABS

42

00. 

Ensure that all lifting equipment is in a safe working order and the area is 

clear of obstructions. Ensure all lifting equipment used has a suitable 

capacity and current testing/compliance.

 

The waste water contained in the ABS

42

00 may contain harmful 

bacteria. Persons coming in contact with wastewater must immediately 

wash and disinfect all exposed areas. Contact your personal physician 

for all health concerns.

 

WARNING - To reduce the risk of electrical shock, all works requiring 

access to the blower box MUST be carried out by a licenced electrician or 

Taylex Accredited Service Agent (TASA) prior to final commissioning.

 

Содержание ABS4200

Страница 1: ...Installation Manual ADVANCED BLOWER SYSTEM 4200 ABS4200 Standard ...

Страница 2: ... 8 9 COMMISSIONING 8 10 EXCAVATION LIFTING INSTRUCTIONS 9 a ABS4200 Excavation Instructions 9 b ABS4200 Lifting Instructions 10 11 ELECTRICAL CONNECTION DIAGRAM 11 12 Note Do not act solely on the basis of the material contained in this document Items herein are general comments only and do not convey advice per say We therefore recommend that formal advice be sought before acting in any of these ...

Страница 3: ...nced if the ABS4200 is not immediately installed SLIPPERY WHEN WET During cleaning maintenance repair work the surrounding area may become extremely slippery due to spilt water Caution is to be taken when walking standing near the ABS4200 when these activities are being conducted Use safe lifting techniques when installing relocating the ABS4200 Ensure that all lifting equipment is in a safe worki...

Страница 4: ...l moisture for heavy equipment access Weather conditions 5 MARK OUT To ensure the ABS4200 is installed in the position nominated by the Home Owner Builder the location of the ABS4200 should be marked out prior to excavation The installer at this stage should have a copy of the approved site plans showing the location of the ABS4200 as well as the required local authority approval If not it is advi...

Страница 5: ...on behind the vehicle before placing it into the prepared hole Maximum reach from the rear of the truck to the centre of ABS4200 will vary depending on the size of the crane To enable the ABS4200 to be unloaded a minimum width of 7m may vary depending on crane truck will be required at the hole This distance allows for the width of the crane truck the width of the tank itself and clearance for saf...

Страница 6: ...Page 6 of 13 ...

Страница 7: ...ion allows for the diversion of storm water and surface waters away from the system Width Height Inlet Height from bottom of tank Inlet Depth from ground level Required Base 5 7mm Drainage Gravel Sand Hole Width Hole Depth TANK 1 2425 2700 2070 530 100 3000 2700 TANK 2 2425 2700 1950 650 100 3000 2700 Refer to Excavation Lifting Instructions on Pages 9 10 STANDARD Taylex ABS4200 NON TRAFFICABLE LO...

Страница 8: ...e inflow outflow direction 1 deviation Backfilling Use sand or excavated material spoil with maximum particle size of 300mm Backfilling of excavation to be completed in not more than 500mm equally distributed layers around the tank perimeter Ensure that sand or excavated material does not fall on the lid of the ABS5000 as this will fall into the system through the manholes and clog the system and ...

Страница 9: ...g is completed prior to having the system commissioned Tanks is full of water 5 000lt each Effluent Disposal area is installed Effluent Disposal Area feed line is connected to ABS4200 Tank 2 Electrical power is connected Tank 1 2 Drains connected main sewer into tank 1 and connection between Tank 1 2 IMPORTANT The Taylex ABS4200 System cannot be commissioned unless power is connected to the system...

Страница 10: ...SE ONLY CERTIFIED LIFTING BARS 2700 mm 1 Always use a Spreader Bar and ensure it is certified 2 Lower chains through TOP lifting holes provided in the lid of the ABS4200 3 Loop chains through the lifting holes directly below on the inside wall of the ABS4200 4 Steel reinforcing bars have been installed inside the concrete for lifting purposes Only lift this tank from these holes 5 If you don t use...

Страница 11: ...d ground level Ensure the installation location including the future landscaping provision allows for the diversion of stormwater and surface waters away from the system NON TRAFFICABLE LOADS ONLY 1 Dig hole 6000mm x 3000mm 2700mm Deep 2 Ensure drainage has a 1 60 fall to the inlet of ABS4200 Risers are available if the tank needs to be installed deeper in the ground to maintain fall 3 Cover base ...

Страница 12: ......

Страница 13: ...Tank 2 ...

Отзывы: