Commissioning
Page 16/40
Installation and starting instruction manual
SYCLOPE TRACE’O
®
A breaker circuit of maximum 10A must be installed near the controller and easily accessible
to stop the main power. It must be identified as a circuit-breaker for the controller!
Before performing the connections, remember to turn off the power!
Use multicore cables if possible!
If not possible, always use a special wiring tip to be sure that wires do not make a contact
together!
Protect the wirings by using electrical clamps.
The
SYCLOPE TRACE’O
®
controller must be connected to the main recirculation pump
system by means of the "remote control" input (CAD) to disallow functionality in the case of
the main pump being stopped.
The controller is protected by a glass time-lag fuse type of 315 mA over-current and by a varistor
against voltage surges over 275 V.
Reference
Name
FUS5X20T315 Time-lag fuse 315mA 5x20 Glass
In case of fuse destroyed, check that the card is not burnt. If this is the case, the complete
card must be changed!
In case of varistor burned, please return the controller to our technical after-sales
department for repairing!
4)
Connection of the primary power supply
The
SYCLOPE TRACE’O
®
controller is equipped with a switching power supply. It is
therefore able to be supplied by an AC voltage used between 90V to 240V - 50/60Hz.
►
Use a 3-point 1.5 mm
2
cable to wire the power supply
►
Strip the 3 wires for 7 mm
►
Pass the 3-point cable through a cable gland
►
Wire the live to 1 and the neutral to 2 of the sector terminal block B1
►
Wire the ground to contact PL1 with the help of an M4 eyelet terminal
►
Tighten the cable gland to ensure tightness
The controller does not have its own independent power switch. It is directly powered when
connected to the main power supply.