background image

 

 

GD_202005_SH5K-30_Quick Commissioning Guide_V1.0 

Page 1 of 5 

 

© Sungrow Australia Group Pty. Ltd. All rights reserved. 

The information in this document is subject to change without notice. 

SH5K-30 Quick Commissioning Guide 

 

Disclaimer  

The material in this document has been prepared by Sungrow Australia Group Pty. Ltd. ABN 76 

168 258 679 and is intended as a guideline to assist solar installers for troubleshooting. It is not a 

statement  or  advice  on  any  of  the  Electrical  or  Solar  Industry  standards  or  guidelines.  Please 

observe all OH&S regulations when working on Sungrow equipment. 

 

The commissioning phase of the SH5K-30 inverter is straight forward and simple. All 

settings are done from the front panel, and there is no longer any need to manually 

enter the battery details 

– the system will automatically detect a powered-up battery. 

 

On first initialisation, the flowing will appear on the LCD screen. 

 Enter to set/check the country code 

 

Enter “AU” for AS/NZS 4777 as default 

 Select  appropriate  DNSP,  or  manually  enter 

grid protection parameters (Default DNSP power factor settings will be loaded) 