SH5K-30 Quick Commissioning Guide
Disclaimer
The material in this document has been prepared by Sungrow Australia Group Pty. Ltd. ABN 76
168 258 679 and is intended as a guideline to assist solar installers for troubleshooting. It is not a
statement or advice on any of the Electrical or Solar Industry standards or guidelines. Please
observe all OH&S regulations when working on Sungrow equipment.
The commissioning phase of the SH5K-30 inverter is straight forward and simple. All
settings are done from the front panel, and there is no longer any need to manually
enter the battery details
– the system will automatically detect a powered-up battery.
On first initialisation, the flowing will appear on the LCD screen.
Enter to set/check the country code
Enter “AU” for AS/NZS 4777 as default
Select appropriate DNSP, or manually enter
grid protection parameters (Default DNSP power factor settings will be loaded)