46
7
Commissioning
7.1
Safety Instructions
High voltage! Electric shock!
•
Wear proper protection equipment before all operations on the device.
•
Do not touch the live terminals or conductors.
•
Respect all safety instructions attached on the device and described in this
manual.
•
Respect all safety instructions prescribed by the manufacturer of devices
connected to the MV Station.
Grid-connection of the MV Station can be performed only after receiving
approval from the local utility grid company and by qualified personnel.
After the MV Station is operating, make sure there are no flammable materials
at least 5 meters around the installation site.
Local/national standards about the min. electric clearance around the MV
Station should be respected.
Make sure the installation is correct and no spare parts or tools are left inside
the device.
Close the doors of the MV Station and the internal devices if the commissioning
process is stopped.
Содержание SG4950HV-MV
Страница 2: ......