28
If it is fixed by welding, it is necessary to weld the bottom of the MV Station to the
foundation. After completion, anti-corrosion treatment should be done on the welding
position.
5.3.4 Installating Oil-Water Separator(Optional)
Generally, if there is no external oil tray, the base of the MV station is used as an oil tray,
and the installation position of the oil-water separator is reserved at the bottom of the
MV Station, as shown in figure A below.
There are two oil-water separator installation positions reserved at the bottom of the MV
station, one is connected to the oil-water separator, and the other installation position
needs to be blocked with a plug.
If the installation of the oil-water separator is needed, please contact SUNGROW
customer service.
System Manual
Содержание SG4950HV-MV
Страница 2: ......