3.
Commissioning
Chapter 3 describes the procedures needed to verify whether your installation of the
SG250K3 is correct and how to start the inverter for the first time.
3.1.
Visual Inspection
To perform a visual inspection of theSG250K3:
1. Verify the grid circuit breaker is open.
2. Verify the DC circuit breaker is open.
3. Inspect the polarity of PV input connections are correct.
4. Check all the mechanical connections and make sure there is no damage,
scratch or abnormal parts
5. Check all the electrical connections and secure the wiring terminals.
Make sure the DC and AC side circuit breakers are switched-off.
6. Check all the wiring of AC and DC sides are connected to the correct
thermals with correct rating wires.
7. Make sure all the bolts that fix the wires are tightened and secured.
3.1.1.
AC Connection Check
It must be verified that the inverter is connected to the correct grid type and that
a right-hand rotary field exists on L
1
, L
2
, and L3. The value of the AC line to line
voltage should be about 400 V.
3.1.2.
DC Connection Check
The DC connections are from the DC combiner boxes to the inverter.
The voltage on the individual DC wires should be almost the same value and
must never exceed the allowable maximum DC voltage.
Besides the voltage values, the polarity of the DC inputs must also be verified. all
DC connections should be checked to ensure that they are
mechanically tight.
3.1.3.
Ground Connection Check
Make sure the ground wire goes through the hole of the ground fault detection
device and connected to the ground copper bar securely.
3.1.4.
Serial Communication Check (Optional)
For external communication monitoring, the data wires must be connected.
Make sure that the RS485 A and B wires are connected correctly and tightened to
the RS485/232 converter.
Make sure the RS485/232 converter DB9 terminal is correctly connected to the
PC DB9 serial port.
Содержание SG250K3
Страница 1: ...SG250K3 Grid Connected Inverter Operation Manual SG250K3 3A E Ver21 200903 Version 2 1...
Страница 2: ...Release History Version Release Date 2 1 Mar 2009 Author Approved By Chen Wei Zhao Wei...
Страница 9: ...Safety Instructions Chapter 1 provides some important safety instructions about SG250K3...
Страница 13: ...4 Introduction Chapter 2 provides basic information about SG250K3...
Страница 18: ...9 Commissioning Chapter 3 describes the verification and commissioning of SG250K3...
Страница 21: ...12 Operation Chapter 4 provides instructions about how to operate the SG250K3...
Страница 24: ...15 Data Interface Chapter 5 describes the LED indicators and touch screen data interface of SG250K3...
Страница 38: ...29 5 History Events 6 History faults 7 History data...
Страница 51: ...42 5 Input the limit data for the running parameter at the Set value column...
Страница 53: ...44 5 Input the limit data for the protection parameter at the Set value column...
Страница 58: ...49 Troubleshooting Chapter 8 gives the basic troubleshooting methods to the customer as a reference...
Страница 62: ...53 Appendix...