30
step 3 Lift the locking part upwards and insert the AC connector into the
AC
terminal on the bottom
side of the inverter. Then press the locking part and secure it with the screw.
step 4 Connect the PE wire to ground and the phase lines and the “N” line to AC circuit breaker.
Then Connect the AC circuit breaker to electric board.
step 5 Make sure all wires are firmly installed via the right torque tool or dragging the cables slightly.
- - End
5.5.4 Assembling the AC Connector (≥ 15 kW)
The AC terminal block is on the bottom side of the inverter. AC connection is the three-
phase-four-wire grid + PE connection (L1, L2, L3, N, and PE).
step 1 Unscrew the swivel nut of the AC connector.
step 2 (Optional) Remove the inner sealing ring if the cable diameter is 19 mm–25 mm. Otherwise
skip this step.