Site Planning for ftServer V 2302, V 4304, and V 6308 Systems
1-1
Chapter 1
Site Planning for ftServer V 2302,
V 4304, and V 6308 Systems
1-
For an overview of required information and tasks you need to perform to prepare a site
for ftServer V 2302, V 4304, and V 6308 systems, see:
“Site Planning Overview” on page 1-1
“Site Planning for Fault-Tolerant Systems” on page 1-2
“Planning for Cables” on page 1-3
“Site Planning Checklist” on page 1-5
“Preparing to Install a System” on page 1-7
“System Documentation” on page 1-9
Site Planning Overview
Site planning for fault-tolerant systems
includes:
Provide electrical power sources that meet the requirements of the system and
optional components, including the purchase of a qualified
.
Plan the location of the system and external components to accommodate the
lengths of the connecting cables.
Provide adequate space for the system or cabinet and for a desk or table to
accommodate components outside a cabinet. Also provide enough space for
servicing the systems and components.
Provide an environment that meets the system's requirements for ambient
temperature and air quality.
Содержание ftServer V 2302
Страница 1: ...Stratus Technologies R624 04 Stratus ftServer V 2302 V 4304 and V 6308 Systems Site Planning Guide ...
Страница 10: ...Preface x Stratus ftServer V 2302 V 4304 and V 6308 Systems Site Planning Guide R624 ...
Страница 47: ...Creating a Floor Plan Space and Component Location Planning 3 11 Figure 3 3 Site Layout Grid 1 square foot ...
Страница 48: ...Creating a Floor Plan 3 12 Stratus ftServer V 2302 V 4304 and V 6308 Systems Site Planning Guide R624 ...
Страница 64: ...AAP87600V PDU Specifications A 8 Stratus ftServer V 2302 V 4304 and V 6308 Systems Site Planning Guide R624 ...