AC Power and HVAC Service Requirements
Electrical Power Planning
2-3
Table 2-1. Worksheet: Determining A-Side Power Requirements
System Component
Quantity
Watts
Watts Subtotal
ftServer systems
x650
Monitor unit
†
† See the
Stratus ftServer Systems: Peripherals Site Planning Guide
(R582) for the wattage
of optional components you purchase from Stratus.
x
Tape drive enclosure
†
x
Storage enclosure
†
x
Fibre Channel switch
‡
‡ If you are using Fibre Channel switches to connect the systems to storage enclosures,
include on this line the power requirements for a Fibre Channel switch. Two switches are
required for fault-tolerant operation. Connect one switch to A-side power and the other
switch to B-side power.
x
User-supplied components
TOTAL A-SIDE POWER REQUIREMENTS
Table 2-2. Worksheet: Determining B-Side Power Requirements
System Component
Quantity
Watts
Watts Subtotal
ftServer systems
x650
Storage enclosure
x
Fibre Channel switch
†
† If you are using Fibre Channel switches to connect the systems to storage enclosures,
include on this line the power requirements for a Fibre Channel switch. Two switches are
required for fault-tolerant operation. Connect one switch to A-side power and the other
switch to B-side power.
x
User-supplied components
TOTAL B-SIDE POWER REQUIREMENTS
Table 2-3. Worksheet: Determining External Power Requirements
System Component
Watts
Other peripheral components
TOTAL EXTERNAL POWER REQUIREMENTS
Содержание ftServer 2510
Страница 1: ...Stratus Technologies R627 04A Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide...
Страница 8: ...Tables viii Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...
Страница 12: ...Preface xii Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...
Страница 46: ...Grounding Requirements 2 18 Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...
Страница 50: ...Planning for Cables 3 4 Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...
Страница 62: ...Modem Requirements for Brazil 4 12 Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...
Страница 68: ...Sample PDU Usage Calculation 5 6 Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...
Страница 96: ...Electrical Power Connectors B 10 Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...
Страница 104: ...Index Index 4 Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...