Preparation Overview Required for Setup
The items listed below are required to
successfully set up and prepare this machine for
operation.
For Lifting
• A forklift or other power lifting device rated
for the weight of the machine.
• Lifting Strap or Chain (rated for at least
1000 lbs.)
For Power Connection
• A power source that meets the minimum
circuit requirements for this machine. (Refer
to the Power Supply Requirements
section for details.)
• A qualified electrician to ensure a safe and
code-compliant connection to the power
source.
For Assembly
• Disposable Rags
• Cleaner/Degreaser
• Disposable Gloves
• Safety Glasses
• Floor Mounting Hardware (As Needed)
• Calipers or Measuring Tape
• Wrench or Socket 17mm
• Dust Collection System
• Dust Hose 4"
• Hose Clamp 4"
• Open-End Wrench 19mm
The purpose of the preparation section is to help
you prepare your machine for operation. The list
below outlines the basic process. Specific steps
for each of these points will be covered in detail
later in this section.
The typical preparation process is as follows:
1.
Unpack the machine and inventory the
contents of the box/crate.
2.
Clean the machine and its components.
3.
Identify an acceptable location for the
machine and move it to that location.
4.
Level the machine and either bolt it to the
floor or place it on mounts.
5.
Assemble the loose components and make
any necessary adjustments or inspections to
ensure the machine is ready for operation.
6.
Connect the machine to the power source.
7.
Test run the machine to make sure it
functions properly and is ready for operation.