5 | Commissioning

14 / 20

Operating instructions sonnenProtect 1300

5 Commissioning

5.1 Commissioning the storage system

It is essential to follow the instructions in the given order when switching on a
storage system with sonnenProtect because the storage system cannot otherwise
function properly.

5.1.1 Switching on the miniature circuit breaker

5

20

40

60

80

100

ON AL

Test

Reset

Illustration 7: Switching on F1.P

„

Switch on the F1.P miniature circuit
breaker for the sonnenProtect.

5.1.2 Switching on the storage system

„

Switch on the storage system as described in the respective operating instructions.

5.1.3 Switching on the grid voltage

„

Switch on the grid voltage using the AC miniature circuit breaker.

5.2 Setting up the sonnenProtect

5.2.1 Establishing connection to the storage system

ü

 The storage system is connected to the router of the home network.

ü

 Your laptop or PC also accesses the home network.

Proceed as follows to access the web interface of the storage system:

„

Enter the address https://find-my.sonnen-batterie.comin the address line of your
browser.

https://find-my.sonnen-batterie.com

Содержание sonnenProtect 1300

Страница 1: ...Operating instructions for operators sonnenProtect 1300 for sonnenBatterie eco 8 2 or eco 9 43 KD 346 Part no 22042 Version X01 info sonnenbatterie de sonnenbatterie de...

Страница 2: ...r Email Document Document number 346 Part number 22042 Version X01 Valid for UK Publication date 19 02 2018 IMPORTANT Read this documentation carefully before installation operation Retain this docume...

Страница 3: ...trol and display elements 9 3 3 Type plate 10 3 4 Symbols on the outside of the sonnenProtect 10 4 Function 12 4 1 Basic principle 12 4 2 Grid operation no grid outage 12 4 3 Emergency operation grid...

Страница 4: ...ed in this document Complete designation Designation in this document sonnenBatterie eco 8 2 Storage system sonnenBatterie eco 9 43 sonnenProtect 1300 sonnenProtect 1 3 Explanation of symbols DANGER E...

Страница 5: ...Information about this document 1 KD 346 22042 EN X01 5 20 Symbol Meaning List Table 1 Additional symbols...

Страница 6: ...es not exceed the nominal power in continuous operation and maximum power when switched on of the sonnenProtect The sonnenProtect must only be used at suitable installation location The transport and...

Страница 7: ...and only when in perfect working order Safety devices must never be overridden blocked or tampered with The interfaces of the sonnenProtect and the storage system must be wired in accordance with the...

Страница 8: ...cy operation approx 5 seconds Dimension Weight Dimensions H W D in mm 235 150 124 Weight in kg approx 2 kg Safety Protection class I PE conductor Degree of protection IP21 Overvoltage category III Pro...

Страница 9: ...ents sonnenProtect 1 sonnenProtect 2 Plug outlet 3 F1 P Z6 miniature circuit breaker 4 K2 P insulation monitor 3 2 2 Control and display elements 5 20 40 60 80 100 ON AL Test Reset 4 6 3 5 2 RAL k F1...

Страница 10: ...ommended setting 100 k V Table 3 Description of the control and display elements 3 3 Type plate The type plate is located on the outer surface of the sonnenProtect The type plate can be used to unique...

Страница 11: ...Product description 3 KD 346 22042 EN X01 11 20 Symbol Meaning Observe the documentation The documentation contains safety information...

Страница 12: ...ge of the sonnenProtect The storage system controls the flows of energy in the building and reserves the set backup buffer 5 20 40 60 80 100 ON AL Test Reset RAL k Illustration 3 Insulation monitor in...

Страница 13: ...his can take a few minutes During this time the plug outlet is supplied with power in emer gency operation 4 4 Protection provided by the insulation monitor The insulation monitor checks the insulatio...

Страница 14: ...it breaker for the sonnenProtect 5 1 2 Switching on the storage system Switch on the storage system as described in the respective operating instructions 5 1 3 Switching on the grid voltage Switch on...

Страница 15: ...th the following password Sonnen2016 The Dashboard page appears Illustration 9 Dashboard page 5 2 2 Setting the backup buffer Proceed as follows to set what percentage of the capacity of the storage s...

Страница 16: ...5 Commissioning 16 20 Operating instructions sonnenProtect 1300 Illustration 10 Settings page...

Страница 17: ...Test key see Control and display elements P 9 Table 4 Checking function 6 2 Cleaning NOTICE Use of unsuitable cleaning agent and or excessive water Material damage because of scratched surfaces and o...

Страница 18: ...ture circuit breaker is switching off immediately or after the sonnenProtect has been operating for a longer period An electrical consumer with a power consumption rating that is too high is connected...

Страница 19: ...tion of the sonnenProtect Danger to life due to electrocution The sonnenProtect must only be uninstalled by authorised electricians 8 2 Disposal Illustration 11 WEEE symbol The sonnenProtect must not...

Страница 20: ...sonnen GmbH Am Riedbach 1 D 87499 Wildpoldsried...

Отзывы: