9 Initial start-up
Display - Connections
Abb. 2-57: Connections on the underside of the display
Access to the rear of the display
►
Lift the cover up and remove it by pulling it for-
ward. (Attention: cable connection present).
Abb. 2-58
9 Initial start-up
i
Initial commissioning of the boiler may only be
performed by qualified personnel
(SOLARFOCUS service technician or
SOLARFOCUS specialist service partner) (=
condition for guarantee, warranty).
Requirements
þ
The boiler is hydraulically connected.
þ
The heating system is filled with water and
has been vented.
þ
The boiler is electrically connected.
Commissioning
►
Connect the boiler to the mains power supply.
►
Carry out the
commissioning routine
in the boiler
control.
Complete the commissioning log, send it
i
Once commissioning is complete, the
completed commissioning log should be sent
to SOLARFOCUS. If this does not happen,
then for guarantee and warranty claims of any
kind the date of shipment from the
manufacturer to the dealer (according to the
delivery note and invoice) will be used.
Commissioning log for biomass heating (see end of
this manual)
DR-0074
10 Shut-down
Disassembly
–
Switch off the boiler and secure it against being
switched back on again.
–
Disconnect the boiler from the power supply.
–
Carry out disassembly in the reverse order to the
installation.
Disposal
–
Observe regional regulations in regard to pro-
per/environmentally-friendly disposal.
–
Recycle the recyclable materials.