Opening Conduit Drill Guides
This section describes how to open drill guides .
CAUTION!
SolarEdge does not permit opening or puncturing the Safety Switch in any
location other than the pre-defined drill guide locations, or otherwise altering
the construction of the enclosure, as this may compromise safety and will void
the warranty. This includes, but is not limited to, the use of fasteners like rivets,
screws, nails, inserts, or pins.
For jurisdictions requiring field applied markings on the Safety Switch
enclosure, such as labels or placards that display PV system information,
adhesive labels or placards that comply with ANSI Z535 and are compatible with
the enclosure material may be used.
ATTENTION!
SolarEdge n'autorise pas l'ouverture or la perforation du commutateur de
sécurité a tout endroit autre que les emplacements de perforation guidés
prédéfinis, ou la modification de l'enceinte électrique, car cela compromettrait
la sécurité et annulerait la garantie. Ceci inclus, sans être limité à, l'utilisation de
fixations comme des rivets, vis, clous, inserts ou des broches.
Pour les juridictions ou un marquage de sécurité est requis sur le couvercle du
coupeur DC, tels que des labels ou étiquettes qui figurent des information du
système PV, des labels ou étiquettes adhésifs compatibles avec ANSI Z535
peuvent être utilisés qui sont compatibles avec le matériau du couvercle.
This step may be performed before or after mounting the inverter.
To open conduit drill guides:
1. Move the Safety Switch and the inverter ON/OFF switch to OFF.
-
Three