Figure 14: CCG RS485 connector
2. Connect the meter's RS485 G, A+, and B- connectors to the
G, A, and B connecters in the inverter.
3. If the SolarEdge device is at the end of the RS485 bus,
terminate as follows:
Inverter - Terminate by switching a termination DIP-
switch inside the inverter to ON (top position). The
switch is located on the communication board and is
marked SW7.
CCG - Terminate by switching the SW2 termination DIP-
switch to ON.
Revenue Grade Energy Meter with Modbus Connection Installation Guide MAN-01-00609-1.0
26
Installing and Connecting the Meter