40 of 73
11.3
Approaching Ramp Operation
This sliding approaching ramp have three following working positions, Customer can
chose any one by their service needs.
a) Fully Retracted Position
See
Figure 37
, this position is for customer with limit space in garage, which
need to fully retract the ramp to close garage door.
Figure 37 – Ramp Fully Retracted Position
b) Normal Working Position
-
See
Figure 38
,
Insert your one hand finger into the handle hole to lift the end sliding
ramp up and raise the middle sliding ramp up slightly;
-
Pull the end and middle sliding ramps out slowly until the middle ramp engage into
Lock A
;
-
Hold the middle ramp in
Lock A
and fully pull the end sliding ramp out, lower the end
ramp to ground and
Lock B
engaged.
-
Adjust the bolt height at the end of the middle sliding ramp, and set the middle sliding
ramp end seat on ground, make sure all locks functioning.
-
After day work, if more clearance space needs for close the garage door, lift the end
sliding ramp end and push back fully, than lift the middle ramp up slightly and push
back to fully retract position see
Figure 37
c) Fully Extended Working Position
-
See
Figure 39
,
Insert your one hand finger into the handle hole to lift the end sliding
ramp up and raise the middle sliding ramp up slightly;
-
Pull the end and middle sliding ramps out slowly until the middle ramp engage into
Lock C
;
-
Fully pull the end sliding ramp out, lower the end ramp to ground and
Lock B
engaged.
-
Adjust the bolt height at the end of the middle sliding ramp, and set the middle sliding
ramp end seat on ground, make sure all locks functioning.
Содержание EELR501A
Страница 6: ...6 of 73 2 0 SAFETY WARNING DECALS...
Страница 8: ...8 of 73 Figure 2 Lift Dimensions Side View Figure 3 Lift Dimensions Back View...
Страница 18: ...18 of 73 Figure 12 Hydraulic Connections...
Страница 33: ...33 of 73 Figure 31 Connection of Air Recoil Hose...
Страница 61: ...61 of 73 16 0 HYDRAULIC AND AIR LINE ASSEMBLY 16 1 Hydraulic Line Routing Map Figure 51 Hydraulic Items Map...
Страница 64: ...64 of 73 16 6 Air Line Routing Map Figure 53 Air Hose Assembly...
Страница 69: ...69 of 73 17 5 Console Labeling Figure 57 Console Labeling...
Страница 74: ...74 of 73 APPENDIX Foundation Plan...