6.0 INSTALLATION OVERVIEW
This is the order in which this installation is to take place:
1. Layout the Bay
2. Unpacking the Lift
3. Inspect the Lift
4. Connect Hydraulic Lines
5. Connect Air Lines
6. Connect Electrical
7. Initial Run of Lift
8. Level, Shim and Anchor
9. Install Accessories
10. Install Front Turnplates
11. Final Check
12. Clean
13. Train Customer on Operation of the Lift
IMPORTANT: Shop air must be connected to the inlet port at the FRL unit on the console.
7.0 INSTALLATION INSTRUCTIONS
When the lift arrives on site please read the owner’s installation and operation manual completely.
Check the contents to make sure no parts are missing before starting installation. Gather all of the
tools listed and make sure that the instructions are fully understood before commencing with the
installation.
IMPORTANT:
It is the user’s responsibility to provide a satisfactory installation area for
the lift. Lifts should only be installed on a level concrete floor with a minimum thickness
of four and a quarter (4¼) inches or 108 mm. Concrete must have a minimum strength
of 3000 psi or 21 MPa and should be aged thirty (30) days prior to installation. Please
consult the architect, contractor or engineer if doubt exists as to the strength and
feasibility of the floor to enable proper lift installation and operation.
IMPORTANT
: It is the user’s responsibility to provide all wiring for electrical hook-up
prior to installation and to ensure that the electrical installation conforms to local
building codes. Where required, it is the user’s responsibility to provide an electrical
isolation switch located in close proximity to the lift that will enable emergency stop
capability and isolate electrical power from the lift for any servicing requirements.
A qualified person should be consulted to address seismic loads and other local or state
requirements.
Содержание EELR501A
Страница 6: ...6 of 73 2 0 SAFETY WARNING DECALS...
Страница 8: ...8 of 73 Figure 2 Lift Dimensions Side View Figure 3 Lift Dimensions Back View...
Страница 18: ...18 of 73 Figure 12 Hydraulic Connections...
Страница 33: ...33 of 73 Figure 31 Connection of Air Recoil Hose...
Страница 61: ...61 of 73 16 0 HYDRAULIC AND AIR LINE ASSEMBLY 16 1 Hydraulic Line Routing Map Figure 51 Hydraulic Items Map...
Страница 64: ...64 of 73 16 6 Air Line Routing Map Figure 53 Air Hose Assembly...
Страница 69: ...69 of 73 17 5 Console Labeling Figure 57 Console Labeling...
Страница 74: ...74 of 73 APPENDIX Foundation Plan...