Version 6.00
Date of editing:
16.09.2022
r.
Page 5 z 11
Installation manual
WKP-O
Figure 4. Installing method of WKP-O fire dampers in rigid wall with KST grille in rigid wall structure.
Страница 1: ...a Installation manual WKP O Fire damper rectangular v https www smay eu ...
Страница 2: ... to make changes to this document TABLE OF CONTENT INSTALLATION TECHNOLOGY 2 I INSTALLATION TECHNOLOGY RIGID WALL 3 II INASTALLATION TECHNOLOGY PROMADUCT CHANNEL 6 III INSTALLATION TECHNOLOGY STRUCTURES THICKER THAN 125 MM 7 IV INSTALLATION TECHNOLOGY LIGHT WALL 8 V INSTALLATION TECHNOLOGY MKW HONEYCOMB MESH COVER 11 ...
Страница 3: ...fire damper by dust and dirt using a foil or other screening material It can prevent components of fire damper by damage Dampers to preserve of the declared resistance insulation and smoke leakage EIS120 EIS90 should be installed on wall which was classified as EIS120 EIS90 It is allowed to install WKP O dampers in wall with other fire resistance should be remembered that fire resistance in this s...
Страница 4: ... undesirable stresses which could lead to deflection of the housing e g by using assembly struts d After setting the fire damper as described fill the gap between the fire damper and the wall with cement cement lime mortar or concrete e After drying of the mortar approx 48 hours remove used supports or suspensions check the fire damper correct operation and leave it in fully open position In order...
Страница 5: ...rsion 6 00 Date of editing 16 09 2022 r Page 4 z 11 Installation manual WKP O Figure 2 Installing method of WKP O fire dampers in rigid wall Figure 3 Installing method of WKP O fire dampers in rigid wall ...
Страница 6: ...Version 6 00 Date of editing 16 09 2022 r Page 5 z 11 Installation manual WKP O Figure 4 Installing method of WKP O fire dampers in rigid wall with KST grille in rigid wall structure ...
Страница 7: ...e of PROMATECT L500 boards with 50 mm thickness must be installed The band around the duct must be made by PROMATECT L500 with 50 mm thickness and 60 mm width Connection of damper and the wall and damper with the band must be made by K84 glue The sides of the duct and the band must be connected by using 4 2x90 4 8x120 screws Figure 5 Installing method of WKP O fire dampers with PROMAT boards duct ...
Страница 8: ...fire dampers are installed in this way that an axis of the fire baffle matches the axis of the wall and ensure a concentricity of fire damper and installation opening In case when wall have more than 125 mm thickness WKP O fire dampers are installed in this way that the damper border is flush with the wall surface Fig 6 Figure 6 Installation method of fire dampers WKP O in structures thicker than ...
Страница 9: ...with a mastic Hilti Firestop Coating CP 673 Promastop Coating Promaseal Mastic or Soudal Firesilicone B1 FR d Put the closed fire damper into the installation opening and support or suspend in this way that an axis of the fire baffle matches the axis of the wall and ensure a concentricity of fire damper and installation opening e After setting the fire damper as described fill the gap between the ...
Страница 10: ...Version 6 00 Date of editing 16 09 2022 r Page 9 z 11 Installation manual WKP O Figure 7 Installation method of fire dampers WKP O in standard wall with 125 mm thick ...
Страница 11: ...Version 6 00 Date of editing 16 09 2022 r Page 10 z 11 Installation manual WKP O Figure 8 Installation method of fire dampers WKP O in standard wall ...
Страница 12: ...nd edge around all perimeter b Honeycomb mesh cover install to the wall with use metal pins for gas concrete 6x32 and with use 5x40 screws c Honeycomb mesh cover install in this way as shown in the figure below Outer edges of openings on left side of mesh cover and on a top and on a bottom must be in line with inner edges of the damper Figure 9 Installation method of MKW B honeycomb mesh cover Fig...