HGM8156 GENSET PARALLEL CONTROLLER USER MANUAL
HGM8156 Genset Parallel (With Mains) Controller 2019-09-10 Version 1.1 Page 34 of 44
10 COMMISSIONING
1) Conduct start, stop and load performance tests on every genset;
2) Parallel every genset with busbar, and do breaker close/open tests;
3) Set every genset (e.g. HGM8151) to Auto Mode;
4) Set HGM8156 in Manual Mode, and make Mains working well, to test whether mains close/open are
normal; when they are normal, open mains breaker;
5) Start HGM8156 manually, after busbar goes normal, test whether busbar close/open are normal;
after they are normal, close mains breaker;
6) Press mains close button, and busbar synchronizes mains; after synchronization mains breaker
closes and starts running in parallel;
7) Conduct load tests and load transfer tests;
8) Set HGM8156 controller to Auto Mode, and controller will start/stop automatically based on settings
and conditions.