![Smartgen HGM8100A Скачать руководство пользователя страница 20](http://html1.mh-extra.com/html/smartgen/hgm8100a/hgm8100a_user-manual_1297525020.webp)
HGM8110A/8120A Genset Controller User Manual Page 20 of 57
4.6
GENSET CONTROLLER ATS CONTROL PROCEDURES
1.
HGM8120A ATS CONTROL PROCEDURES
1)
If input port is configured as Closed Auxiliary
A.
If “Open breaker detect” is “Enable”
When transferring load from mains to generator, controller begins detecting “fail to transfer”, then the
open delay and transfer rest delay will begin. When detecting time out, if switch open failed, the
generator will not switch on, otherwise, generator switch on. Detecting transfer failure while generator
switch on. When detecting time out, if switch on fail, it needs to wait for generator switch on. If transfer
failed and warning is “Enable”, there is alarming signal whatever switch on or off failure.
The way to transfer from generator load to mains load is as same as above.
B.
If “Open breaker detect” is “Disable”
Mains load is transferred into generator load, after the delay of switch off and transfer interval,
generator switch on. Detecting transfer fail while generator switch on. After detecting time out, if switch
on fail, then wait for generator switch on. If transfer fails and warning is “Enable”, there is alarming
signal.
2)
If input port is not configured as Close Auxiliary
Mains load is transferred into generator load, after switch off and transfer interval delay, generator
switch on.
The way to transfer generator load to mains load is as same as above.
2.
HGM8110A ATS CONTROL PROCEDURES
1)
If input port is configured as Closed Auxiliary
A.
If “Open breaker detect” is “Enable”
Generator load is transferred into generator un-load, after the delay of switch off, detecting transfer
failure while switch off output. When detecting time out, if switch off failed, it will wait for switch off.
Otherwise, switch off is completed.
Generator unload is transferred into generator load, after the delay of switch on, detecting transfer
failure while switch on outputting. When detecting time out, if switch on failed, it will wait for switch on.
Otherwise, switch on is completed.
If transfer failed and warning is “Enable”, there is alarming signal whatever switch on or off failure.
B.
If “Open breaker detect” is “Disable”
Generator load is transferred into generator unload, after the delay of switch off, switch off is
completed.