6 Maintenance
SMA Solar Technology AG
Maintenance Manual
SCCP-JP-B1-WA-en-22
46
3. Check whether the DC load-break switch is switched off and indicating the
Off
position.
If the DC load-break switch is not switched off or not indicating the position
Off
, contact (see Section 9 "Contact",
4. Close the doors of the interface cabinet.
5. Switch the inverter to
Start
.
6. Open the doors of the interface cabinet.
7. Check whether the DC load-break switch is switched on and indicating the position
On
.
If the DC load-break switch is not switched on or not indicating the position
On
, contact (see Section 9 "Contact",
8. Switch the inverter to
Stop
.
9. Test the switching process three times.
10. Close the doors of the interface cabinet.
6.4.1.2
Checking the AC Disconnection Unit
The inverter is optionally equipped with an AC disconnection unit. If a circuit breaker manufactured by ABB is installed,
it needs to be checked.
Figure 12: Switch positions of the AC disconnection unit from ABB
Position
Designation
Explanation
A
Switch position
on
The AC disconnection unit is closed.
B
Central switch position
The AC disconnection unit was tripped and is open.
C
Switch position
off
The AC disconnection unit is open.
Содержание Sunny Central 1000CP-JP
Страница 68: ...www SMA Solar com...