COMMISSIONING
31
© SMA Solar Technology AG Subject to changes to the technical content! Version 1.1 Last updated 04/2021
7
Tap next to the display once more to call up the next menu item. The dis-
play will now show the assigned IP address which must start with
192.168.4. ...
8
The STORAGE-67-TS-10 will switch to INIT mode and “SWITCH”
17
will start flashing.
9
Start the commissioning process of the STPS 60-10 with the LCS tool.
The software and instructions are located on the USB drive
18
.
When
the commissioning process is successfully completed, the
STORAGE-67-TS-10 will enter pre-charge mode (PRECHG).
10
Once pre-charging has completed, “SWITCH”
17
will remain lit. The
status “Ok” will be shown on the display of the SMA HV APU. The
STORAGE-67-TS-10 is now ready for operation.
NOTE
The display will remain active for about two minutes before being deactivated. It can be reactivated by
tapping twice.
8.2 Commissioning of STORAGE-67-TS-10 systems following the master/
slave principle
ATTENTION! Risk of damage to the battery due to incorrect configuration.
Improper configuration can result in damage to the battery. The parameters settings affect the charging behavior
of the STPS 60-10. It is therefore important to set the parameters correctly during commissioning.
Requirements
The STPS 60-10 has been installed in accordance with the installation and connection specifications.
Procedure
1
Check the cabling of the STPS 60-10 and the STORAGE-67-TS-10 (see the STPS 60-10 installation guide).
2
Check the cabling of the components in accordance with section “5.5 Battery module wiring“ on page 17 et
seq. If the cabling is correct, all live components will be protected against physical contact. Switch DC circuit
breaker in the BatBreaker (if applicable) to “ON.” Make sure that the STPS 60-10 DC load-break switch is set to