Electrical Connection
SMA Solar Technology AG
20
SL6000-TEN081820
Technical Description
Connection procedure for three load resistors
1.
Unscrew the M25 metric-thread cable screw connection's lock nut (A) and slide it over the
load resistor cable.
2.
Pull the load resistor cable through the cable screw connection.
3.
Ground the shield using the EMC cable screw connection.
4.
Ground the housing of the load resistor by connecting it to the "PE" connection terminal.
5.
Connect the first load resistor to "X51"and "X61". Connect the second load resistor to "X52"
and "X62". Connect the third load resistor to "X53" and "X63".
6.
Tighten the lock nut on the cable screw connection.
7.
Ensure that the load resistors are connected properly.
NOTICE!
A short circuit will irreparably damage the Smart Load.
•
Always connect three load resistors, with a power consumption of 2 kW each, for
a 3-phase AC connection.
DANGER!
Danger to life due to high voltages in the Smart Load.
•
Only start the stand-alone grid system after all cables have been connected.