SMA
Technologie AG
Opening and Closing the Sunny Boy
Installation Guide
SBTLHCMS-IEN080411
Page31
7 Opening and Closing the Sunny Boy
7. 1 Opening the Sunny Boy
1.
Switch the line circuit breaker to the "off" position.
2.
Remove the Electronic Solar Switch.
3.
Immediately remove the DC cables from the Sunny Boy in order to completely dis-
connect the PV-generator from the Sunny Boy.
4.
Wait 30 minutes!
5.
Remove the four screws from the enclosure cover and pull the cover forward
smoothly. Remove the PE connection from the cover. Loosen the locking on the PE
connectors on the cover when you remove them.
Notice!
If you need to open the device for whatever reason, please pay attention
to section 3 "Safety Instructions" (Page 9).
Notice!
Follow the sequence below under all circumstances.
Содержание SB 4200TL HC
Страница 2: ......
Страница 6: ...Explanation of the Symbols Used SMA Technologie AG Page 6 SBTLHCMS IEN080411 Installation Guide...
Страница 10: ...Safety Instructions SMA Technologie AG Page 10 SBTLHCMS IEN080411 Installation Guide...
Страница 30: ...Installation SMA Technologie AG Page 30 SBTLHCMS IEN080411 Installation Guide...
Страница 44: ...Technical Data SMA Technologie AG Page 44 SBTLHCMS IEN080411 Installation Guide...
Страница 46: ...Inspection of the Electronic Solar Switch SMA Technologie AG Page 46 SBTLHCMS IEN080411 Installation Guide...
Страница 60: ...The Communications Interface SMA Technologie AG Page 60 SBTLHCMS IEN080411 Installation Guide...
Страница 63: ......