Loading/Unloading
Section 3 - Operation
3.10 Loading/Unloading
Know and heed all national, state or territorial/provincial
and local rules which apply to your loading/unloading
of aerial platforms.
Only qualified personnel shall operate the aerial
platform during loading/unloading.
Be sure vehicle capacity and loading equipment
hoists, chains, straps, etc., are sufficient to withstand
maximum aerial platform weight.
The transport vehicle must be parked on a level surface
and must be secured to prevent rolling while aerial
platform is being loaded/unloaded.
3.10-1 Lifting
WARNING
Only qualified rigger shall operate
machinery during lifting.
When it is necessary to lift the Skyjack aerial platform
the following conditions must be met:
• The platform must be fully lowered.
• The main power disconnect switch must be in
“ ” off position.
• The hydraulic/electric and battery trays must be
closed and securely latched.
• The extension platform must be retracted and
secured.
• The platform control console must be secured to
the railings or removed.
• The platform must be cleared of all personnel,
tools and materials.
• The lifting/rigging must be attached to all four
lifting points as illustrated in
Figure 3-14.
Tie down/lifting
points
Tie down/lifting
points
Figure 3-14. Tie Downs/Lifting Points
Center of
gravity
Center of
gravity
Figure 3-15. Center of Gravity
Page 52
SJIII DC Electric
Содержание 3219 SJIII Compact Series
Страница 12: ...Page 12 SJIII DC Electric Notes ...
Страница 60: ...Page 60 SJIII DC Electric Notes ...
Страница 103: ......
Страница 104: ...www skyjack com Pålitelig lift løsninger av folk som bryr seg ...