SKF TKSA 60 Скачать руководство пользователя страница 1

TKSA 60 / 80 Display Units 
 

 

 

 

 

  Power on / off (hold for two seconds to turn off) 
  Battery status indicator 
  Wireless communications status with measuring units 
  Navigate display screens and select highlighted item 
  Cancel (C) button - delete last character typed 
  Battery charging LED indicator 
  Alpha/numeric data entry keypad 

 

TKSA 60 / 80 Measuring Units 

 

  Lasers 
  CCD sensors and sensor grids 
  Pitch adjustment knob 

 

  Measuring unit on the stationary machine 
  Measuring unit on the movable machine 
  Movable machine 

 
The above clock positions (9, 12, and 3 o’clock) are the most 
common for alignment measurements; however, measurements 
can be taken from any clock position.  Also, while it is strongly 
recommended to take measurements that are 90 degrees apart, 
the TKSA 60 / 80 Alignment Tools will accept a minimum rotation 
angle of 30 degrees from the previous measurement position. 
 

The Display Unit - Home Screen 

 

 
When first powered on, the Display Unit displays its Home screen. 
 

Icon  Description 

 

Display unit’s battery status 

 

Wireless communication status with measuring units 

  Length units of measurement 

  Initiate a Quick Alignment 

  Initiate a Quick Soft Foot job 

  Set up and perform a Full Alignment job 

  Open a previously stored alignment job  

  Export reports to a USB memory stick for transfer to PC 

  Modify system settings 

 
Two Alignment Method Options 

The TKSA 60 / 80 Alignment Tools provide two methods for 
performing alignment inspections: 

 

Quick Alignment 

The Quick Alignment feature is designed to allow you to quickly 
perform an alignment inspection on a motor / pump machine train.

 

 

Full Alignment Job 

Full alignment jobs require more setup at the beginning of the 
alignment job and provide a more structured alignment job 
process.  Also, you can specify alignment inspections on machine 
trains other than motor / pump machine trains, including machine 
trains consisting of more than two machines. 
 

To Modify System Settings: 

  From either the Home screen or the right panel menu, select 

the Settings icon to display the main Settings screen.  Then specify 
Display Unit settings, Measuring Unit settings, Units of 
Measurement settings, and Date and Time settings. 

 

Standard Alignment Job Process 

Set up the job

 – Set up the two alignment measuring units; input 

machinery dimension information, and alignment targets and 
tolerances. 

Perform as-found inspections

 – Perform initial measurements 

for the alignment inspection and for other selected inspections. 

View results

 – View as-found inspection results and determine 

whether corrections are required for each inspection. 

Make corrections

 - If corrections are required, make corrections 

for each inspection requiring correction. 

Perform a final as-corrected alignment inspection

 – After all 

corrections are made, re-inspect machine alignment to verify 
accuracy and record as-corrected job results. 

Save the Job

 – Save the job for historical reference and for use 

with future alignment jobs. 
 

To Perform an Alignment Inspection: 

 
1 – Turn off power to the drive machine. 
2 – Attach and adjust the v-brackets and measuring units as 
described in the user manual.  Laser lines should hit the centre of 
the other unit’s white sensor grid. 
3 – Power on the measuring units and display unit. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Отзывы: