Commissioning
Instruction Manual FireGuard 2
13542E/5
35
6
Commissioning
The initial start-up of the web user interface via the optional WLAN interface is described in
the Reference Handbook.
Proceed with the initial start-up in accordance with the following table:
WORKSTEP
ADDITIONAL INFO / IMAGES
1.
Ensure that all components are correctly
mounted and connected.
2.
2.1: Establish the service voltage to the instru-
ment.
2.2: Plug the SICON-C into the instrument ac-
cording to Section 7.3and wait until the wel-
come screen appears in the display.
The factory setting language is English.
2.3: The instrument is ready for measure-
ment.
3.
Set the language.
Section 8.1
4.
Set the limits.
Section 8.2
5.
Set the outputs.
Section 8.3
6.
Configure the adjustment.
Section 8.4
7.
If an optional Profibus module is present, set
the Profibus parameters.
Section 8.5
8.
If an optional Profinet IO module is present,
set the Profinet parameters.
Section 8.6
9.
If an optional Modbus module is present, set
the Modbus parameters.
Section 8.7
10. If an optional StromRel module is present, set
the current outputs.
Section 8.8
11. Enter the access code.
Section 8.9
12. Carry out recalibration.
Section 9.4
13. Back up the configured data.
Section 8.10