UTMC OTU/MOVA Handbook
667/HB/31601/000
Page 77
Issue 5
7.2 MOVA COMMISSIONING CHECKLIST
The following checklist should be used to commission MOVA. The steps are expanded
upon in the sections referenced.
Step Section
Action to be Performed
1)
Check that the outstation has been installed correctly.
2)
-
Switch on the outstation’s mains supply.
3)
5.3.1 Check that the System LED (LP1) is flashing.
4)
7.3.1 Start the MOVA applications.
5)
7.3.2 Use the appropriate MOVA Comm shortcut to connect to the
required MOVA stream.
6)
7.3.3 If MOVA is to use a Bus / MOVA (Digital) I/O Board, check that the
correct type of I/O boards have been detected, using the ‘cards’
command.
If MOVA is to use the serial link to an ST700/750/800/900 family
controller check that the link is active – View the ‘Controller Files’
web screen and check that the ESP link status is not ‘link down’.
7)
7.3.4 Set the time and date in the outstation.
8)
7.3.5 Enter the correct MOVA licence codes.
9)
7.4.1 For MOVA 7 if log file export to an OSS logging is to be used set up
the export start time and period and enable the OSS
10
7.4.3 For MOVA 7 enable alerts if required
11)
7.3.6 Configure the MOVA site Names
12)
7.3.7 Import MOVA detector and control/reply bit mapping
13
7.3.8 Download the site data into the MOVA unit from the PC.
14
7.3.9 Use the commissioning screen to check for following.
a) MOVA is currently not enabled (MOVA enabled = 0)
b) The Controller is ready* (CRB = 1)
c) The Confirm bits are all set to ‘1’, except for the current stage
which should be set to ‘0’.
Watch the controller perform at least one complete cycle to check
that each stage and phase confirm bit is being activated correctly by
the controller.
* If UTC is active, request the MO bit to be set to allow MOVA control
(or else apply local UTC override) since UTC will inhibit the
‘Controller Ready Bit’.